Apple makes California solar deal

Thursday, February 12, 2015

Electronics manufacturer Apple has announced an $848 million deal to buy electricity from a solar energy project to be developed in California. Project developer First Solar has described the power purchase agreement as "the largest agreement in the industry to provide clean energy to a commercial end user."

Solar photovoltaic panels in the Utah desert.

Earlier this week, Apple announced the deal with First Solar, Inc., to buy power from First Solar's California Flats Solar Project in Monterey County, California.  Under a 25-year power purchase agreement or PPA, Apple will buy the equivalent of 130 megawatts of the solar project's output. 

First Solar is a vertically-integrated solar company, manufacturing solar photovoltaic panels, developing utility-scale photovoltaic power plants, and providing solar project support services.  First Solar boasts involvement with over 10 gigawatts of installed solar photovoltaic capacity worldwide.  Its resume includes the 550-megawatt Topaz Solar project in California and the 290-megawatt Agua Caliente project, which was once the world's largest operating solar energy project.

First Solar's California Flats Solar Project will occupy a 2,900-acre site on the Jack Ranch in Cholame, California.  Owned by Hearst Corporation, the project site was formerly a dryland farm, and occupies about 3% of the Jack Ranch property.  First Solar expects to begin construction later this year, and to complete the project by the end of 2016.

With a total project capacity of 280 megawatts, Apple's 130-megawatt commitment covers about 46% of the project's output.  The project's remaining 150 megawatts will be sold to utility Pacific Gas & Electric under a separate long-term PPA.

Apple has developed other renewable energy projects, including fuel cells and solar panels at its Maiden, North Carolina data center.  Other high-tech companies have also made significant investments in renewable energy, including Google's commitment of over $1.5 billion to solar and wind projects through power purchase agreements and direct investments.

eBay OKed for wholesale electricity sales

Friday, September 13, 2013

As customer-sited electric generation becomes increasingly economic, major companies outside the energy sector are entering electricity markets.  Federal regulators this month granted eBay Inc.'s request for authorization to sell electricity at wholesale.  What does this mean?

U.S. wholesale electricity markets are generally regulated by the Federal Energy Regulatory Commission.  Most sellers in those markets are regulated as public utilities - but in recent years, the category of "utilities" has expanded beyond the traditional vertically-integrated utility serving retail customers with electricity.  The growth in this sector has come largely from end-users of electricity who have developed on-site generation to meet their needs - and to sell excess power into wholesale markets.  Recent big-name entries into the wholesale electricity market include Google Inc. and Wal-Mart Stores Inc. - and now eBay.

On September 5, 2013, the Commission granted eBay market-based rate authority.  This approval enables eBay to sell electric energy, capacity, and other products.  As described in the Commission's order, eBay plans to own and operate a 6 megawatt fuel cell generation facility located at its data center in South Jordan, Utah.  In a June 21 filing, eBay described plans to install five natural gas-fueled "Bloom Box" units at the data center to provide power to run the facility. 

eBay's plans bear some resemblance to the fuel cell system Apple developed at its data center in Maiden, North Carolina.  Data centers consume significant amounts of energy, both for processing and for cooling.  In many cases, on-site generation projects offer data centers a way to cut costs while improving their reliability and their environmental footprint.

Maximizing the cost-effectiveness of a distributed generation project requires it to be sized appropriately for the load to be served.  In some applications, there may be little to no excess power available for sale at wholesale to the grid, while other on-site generation projects may be capable of exporting significant amounts of energy to the grid.  With its market-based rate authorization in hand, eBay stands ready to enter the wholesale market with any excess power its Utah fuel cells produce.

Biogas at Apple's NC data center

Thursday, May 10, 2012

Continuing to look at Apple's plans for energy supply at its data center in Maiden, North Carolina:

This spring a series of filings by Apple to the Federal Energy Regulatory Commission gave the public some insight into Apple's planned electric generation facilities at the Maiden data center, home to Apple's iCloud service.  (See Tuesday's blog entry for a look at its solar photovoltaic project, and Wednesday's entry for its fuel cell project.)

Fuel cells convert fuels into electricity through a chemical process that does not rely on combustion.  According to one of Apple's filings with FERC, Apple plans to use biogas to power its fuel cells:

The Systems will be fueled with biogas that will be transported via a natural gas pipeline system.  To be injected into the natural gas pipeline system and qualify as pipeline-grade gas, biogas must meet strict heat content and quality requirements.  Consequently, raw biogas must be upgraded (i.e., cleaned and separated to remove components such as hydrogen sulfide, chlorine, and sulfur and to increase methane content) prior to being injected into a pipeline.  Once injected into the pipeline system, it comingles with conventional natural gas and is indistinguishable from conventional natural gas in terms of safety and burning quality.  The biogas, having been upgraded/cleaned to pipeline-quality and then injected into the natural gas pipeline system displaces a comparable quantity of conventional natural gas.
The volume and heat content of the biogas will be measured at a utility-grade meter at the point of injection.  The biogas will then enter the natural gas pipeline infrastructure that has an established balancing measurement system regulated by the Federal Energy Regulatory Commission (Commission).  The biogas will be nominated for the Facility in accordance with the pipeline’s posted business practices and relevant Commission requirements.  Not only the contract and purchase of biogas, but also the nomination process demonstrates compliance with 18 C.F.R. § 292.204 (b).  A utility-grade meter at the Facility will measure actual gas consumption by the Facility.  A revenue-grade meter will measure electricity generated by the Facility.

Furthermore, because the biogas can be upgraded to flow in a pipeline system and nominated for a particular facility, it allows for flexibility in the location of the generating unit.  This flexibility will provide for increased efficiency (operational and maintenance), enhanced reliability, and improved land use. These benefits were recognized by the North Carolina Utilities Commission (“NCUC”).  The NCUC ruled that biogas fuel, which is derived from a renewable energy resource, cleaned to pipeline quality, injected into the pipeline system and nominated for an electric generation facility within the state of North Carolina, is a renewable energy resource known as “Directed Biogas” (NCUC Order Issued March 21, 2012, in docket SP 100, Sub 29). 

This Facility is in keeping with the stated reasons for the implementation of the Public Utility Regulatory Policies Act of 1978 (PURPA), specifically the increased conservation of electric energy, increased efficiency in the use of facility and resources by electric utilities, and the conservation of natural gas.  In the case of this Facility, the use of biogas, which displaces conventional natural gas, to generate electricity will reduce greenhouse gas emissions and smog forming pollutants while also diversifying the fuel used to generate electricity.  The Systems that make up this Facility consume less fuel and produce less CO2 than other technologies.  Each System emits less than 0.07 lbs/MW-hr of NOx , negligible SOx, less than 0.10 lbs/MW-hr of CO and less than 0.02 lbs/MW-hr of VOC.  Additionally, the Systems require very little water, with an average usage of approximately 0.00001 gallons/kWh. The low carbon footprint, de minimus criteria pollutants, small land use and negligible water use, make this Facility a prime example of an initiative that furthers the Commission’s stated goal of increasing renewable energy and investing in environmentally beneficial technologies.

Apple's Maiden, NC fuel cell project

Wednesday, May 9, 2012

Following on yesterday's look at Apple's planned solar photovoltaic system for its Maiden, North Carolina data center, here's a look at the fuel cell project Apple is also planning the Maiden facility.

A public filing Apple made last month to the Federal Energy Regulatory Commission describes the Maiden data center's proposed fuel cell system.  The filing represents Apple's self-certification that the fuel cell project meets the standards of the Public Utility Regulatory Policies Act (PURPA) of 1978 as a "qualifying facility", setting the facility up for incentives that could include the right to require Duke Energy Carolinas to buy its output.

Apple's fuel cell self-certification filing, docketed by FERC as QF12-327, describes the project:

The Facility will consist of 24 fuel cell systems (“Systems”) using a patented solid oxide fuel cell technology to generate electricity.  A single fuel cell consists of an anode, a cathode and an electrolyte placed between the two electrodes.  As fuel flows in through the anode side and an oxidant comes in over the cathode, a reaction is triggered that causes electrons to move into the fuel cell’s circuit, producing electricity.

Each System consists of thousands of fuel cells stacked together.  Multiple stacks are aggregated together into a "power module", and then multiple power modules, along with a common fuel input and electrical output are assembled as a complete system.  Each System is approximately the size of a standard parking space and will produce approximately 200 kW of power.  The Systems have a modular design that allows the simultaneous use of multiple Systems in order to achieve the desired electric generation output.  Each 200 kW (AC) System is comprised of six individual direct current (DC) power-producing modules and one input/output module for fuel intake and electricity output.  Each of the six individual DC power producing modules is feeding electricity to the input/output module which converts the DC power into the systems AC power output.  The combination of six DC modules and one input/output module comprise a 200 kW (AC) all-electric System.  Each System has a net baseload generating capacity of 200 kW (AC).  The total generating capacity of the Facility will be approximately 4.8 MW (AC).
The "patented solid oxide fuel cell technology to generate electricity" in this description is reported to be Bloom Energy's Bloom box technology.

Tomorrow, a look at the innovative fuel Apple proposes to use to power these fuel cells.

Apple's Maiden NC solar project

Tuesday, May 8, 2012

As Apple continues to develop a data center to handle its iCloud service, some details are emerging about the energy infrastructure to be built at the Maiden, North Carolina facility.  Two public filings Apple made last month to the Federal Energy Regulatory Commission describe the Maiden data center's solar photovoltaic and fuel cell systems.

Under federal law, certain efficient or renewable electricity generation facilities can certify themselves as "qualifying facilities" or QFs.  The Public Utility Regulatory Policies Act (PURPA) of 1978 required monopolistic electric utilities to buy power from QFs, as long as that cost was less than the utility's own "avoided cost".  Generally, a utility's avoided cost is the cost of the power the utility would have procured from a source other than the QF in question.  This policy was intended to improve the efficiency of the nation's fleet of electric generation, as lower-cost QFs displaced more expensive traditional utility generation.

In April, Apple submitted two filings to FERC certifying its planned Maiden solar and fuel cell systems as QFs.  These documents provide additional insight into Apple's plans.

In its solar photovoltaic project self-certification, docketed by FERC as QF12-328, Apple described the project:
Each of the photovoltaic installations will consist of multiple 435-watt photovoltaic modules on ground-mounted single-axis tracking systems. The current design includes 57,360 435-watt modules. The modules will be connected in series strings of 10 to achieve the appropriate DC voltage. The modules will track the sun by rotating about a north-south axis. At the current time, we expect 14 photovoltaic installations will make up the solar farm: ten 1.50 MW installations and four 1.25 MW installations. The final number of installations and modules will depend on detailed design considerations in consultation with the utility, the photovoltaic system provider, and local permitting authorities. Each installation will be connected to two 750 kW or two 625 kW inverters. Inverters will convert the DC current produced by the systems to AC current. A step up transformer is installed between the inverter outputs and the point of connection to Duke's distribution system. Each installation has a dedicated transformer. The photovoltaic installations will be installed in a phased manner, whereby the installations will be interconnected as they are completed.

Check out tomorrow's blog entry for a look at Apple's biogas fuel cell facility.


Debate over data center green claims

Friday, April 20, 2012

How green is Apple's iCloud data storage service?  That question provoked debate this week, as environmental activism group Greenpeace released a report critical of Apple's choices of power supply for its data center in Maiden, North Carolina, where the iCloud storage is based.

Greenpeace's report, How Clean is Your Cloud (52-page PDF), notes the explosive growth of cloud-based data and computing services offered by companies like Apple, Facebook, Amazon, Microsoft, Google,
and Yahoo.  These services are made possible by data centers, centralized networks of servers and computer infrastructure.  As Greenpeace put it, "Data centers are the factories of the 21st century information age, containing thousands of computers that store and manage our rapidly growing collection of data for consumption at a moment’s notice."

Data centers can be major consumers of electricity, needing cooling and air handling as well as energy for raw processing operations.  Some data center operators seek out renewable electricity, while others are developing on-site generation.  Most work to improve their energy efficiency, making the best possible use of the energy they need.

Apple has touted the green credentials of its Maiden data center, which was designed to earn LEED Platinum certification from the U.S. Green Building Council.  Apple's Maiden facility will also include a 20 MW solar facility on land adjacent to the data center, as well as a 5 MW biogas-based fuel cell system, systems Apple describes as "the nation’s largest end user-owned solar array" and "the largest nonutility fuel cell installation in the United States."

Greenpeace's report notes that despite these investments, Apple's data center is located in an area where utilities source a significant amount of power from coal-fired power plants.  Greenpeace and Apple dispute how much power the Maiden plant will consume (differing by as much as a factor of 5), and thus what fraction of its electricity will be produced from renewable on-site generation.

Whatever the facts may be, the debate illustrates society's interest in the environmental impacts of our technological choices - as well as the difficulty in evaluating some claims of greenness.