Continuing my look at dams targeted for removal: today, the Great Works dam on the Penobscot River in Maine.  This is an interesting tale of mills, dams, changes in ownership, and changes in use.  Like the Briggsville Dam in Clarksburg, Massachusetts, the Great Works dam was built to support a mill -- but like the Boston Felt dam, the Great Works dam produced renewable power.

The Great Works Hydroelectric Project (FERC project no. 2312) is located adjacent to the Old Town mill (which has changed hands over the years, and is now owned by Old Town Fuel and Fiber).  Originally built in the late 1800s, the Great Works project's FERC license was issued in 1963, with an original expiration date of March 31, 2002.

In its most recent incarnation, Great Works consisted of a powerhouse containing 11 turbine-generator units totaling about 8 MW of installed capacity; a non-overflow section with two operating fishways and three gated outlet pipes (one 6 foot square, two 9 foot diameter); and a spillway equipped with flashboards extending from the non-overflow section across the river to the east river bank in the Town of Bradley. The total length of the Project is approximately 1,353 feet. The dam forms a 128-acre impoundment at a normal impoundment elevation of 81.73 feet. The tailrace is separated from the main river by an earthen dike and the powerhouse discharges to the tailrace. The presence of the earthen dike creates a bypass reach of approximately 1,200 feet in length, and approximately 1,000 feet of which is a backwater. The project also includes two operating Denil-type fish ladders, one located in the tailrace, the other at the west end of the spillway. An older abandoned fish ladder is located near the center of the spillway.

In March 1997, James River Paper Company owned both the mill and the dam.  James River filed a notice of intent to file an application for a new license.  Shortly thereafter, the dam changed hands to PPL Great Works, LLC.  In 2003, Commission staff suspended the processing of the project's relicense application to allow negotiation of a multi-project, "basin-wide settlement agreement" - a comprehensive agreement covering water flows and dams throughout the Penobscot River watershed.

That agreement - the Lower Penobscot Basin Comprehensive Settlement Accord - ensued on June 25, 2004.  Seven conservation groups, hydroelectric company PPL Corp., the Penobscot Indian Nation and state and federal agencies, agreed to the removal of both the Great Works and Milford dams as well as the removal of flashboards and the installation of a fish bypass at the Howland Dam. 


Pursuant to the settlement agreement, on November 7, 2008, PPL Great Works and the Penobscot River Restoration Trust (Trust) filed an application to transfer the license to the Trust, and the Trust filed an application to surrender the license for the Great Works Project and remove the project’s dam.

On June 16, 2010, FERC issued its order approving the surrender of the project license (29 page PDF of the order).  In its order, FERC described the process to be used in removing the Great Works dam:

The Great Works Project impoundment would be drawn down through the opening of gates and removal of the flashboards. Then, an upstream access road would be constructed from the east bank along the entire length of the spillway. Another road would be constructed downstream out to mid-channel to allow removal of the abandoned fish ladder. The spillway would be removed in sections from west to east with concurrent removal of the access road. Following this, another road would be constructed from the west bank across the upstream side of the powerhouse. From this road, the remaining portion of the spillway immediately adjacent to the powerhouse would be removed along with the two operational fish ladders. The forebay area would be filled and graded and the access road removed. The project’s powerhouse is proposed to remain because it houses equipment for an adjacent pulp mill.
Removal of the Great Works dam may occur in 2012, bringing a close (or at least a new chapter) to this tale of a mill and its dam.  In this case, the greater Lower Penobscot Basin Comprehensive Settlement Accord and the actions of the Penobscot River Restoration Trust played a major role.  In a coming edition, I'll look at the policy considerations that went into that settlement agreement, including the promises of both improved sea-run fish passage and continued hydroelectric generation elsewhere on the Penobscot River.

October 28, 2010 - Maine dam removal?

Thursday, October 28, 2010

Fiery fall foliage in Phippsburg, Maine.
Yesterday, I mentioned a list of recently-removed Maine dams.  That list describes 20 dams as having been removed as of January 1, 2010, with another ten dams described as "currently proposed or under study for removal":


* Boston Felt Dam Lebanon, ME & Rochester, NH Salmon Falls River

* Coopers Mills Dam Whitefield Sheepscot River

* Gardiner Paperboard Dam Gardiner Cobbosseecontee Stream

* Great Works Dam Old Town & Bradley Penobscot River

* Montsweag Dam Wiscasset & Woolwich Montsweag Brook

* Veazie Dam Veazie & Eddington Penobscot River

* West Winterport Dam Winterport & Frankfort Marsh Stream

* Juliet Mill Dam Lisbon Sabattus River

* Farwell Mill Dam Lisbon Sabattus River

* Martin Brook Upper Dam Madawaska Martin Brook

Of these, several more have been removed.  For example, the Montsweag dam is gone.  The West Winterport dam is also gone.

Let's take a deeper look at one of the dams on this list.  The Boston Felt dam (Project No. 4542–013), which formerly produced 150 kW, was granted an exemption from licensing on August 29, 1983 (24 FERC ¶ 62,240). The project stopped operations in May 2006, due to a breach of the project dam by high river flows.  Project owner Bacon Felt Company, Inc., stated that a 20-foot long, 6-foot wide section of the wooden frame dam was carried away by the flooding.

After the water level dropped, the Federal Energy Regulator Commission ordered the owner to repair the dam.  US Fish and Wildlife Service also gave a directive regarding the installation of fish passage.  The owner allegedly explained why the project was inoperable (damage to the dam) and told FERC that resumption of generation at the project may be beyond its available resources, and said it would file a compliance plan and progress reports.  By September 2009, FERC issued a notice of revocation of exemption by surrender, based on allegations that exemptee had not taken responsive action.

In an October 2009 response, Bacon Felt filed a protest, stating that it had in fact replied to the Commission's information request and had requested a 120-day review period.  By February 2010, the project owner filed a formal motion requesting withdrawal of the notice of revocation of its exemption to maintain the project.  Bacon pointed to a host of changes, including a change in ownership of the company, changes to their manufacturing strategy, and an overall increase in the price of purchased power.  Bacon then argued that it had not surrendered its exemption, nor had it abandoned the project triggering an implied surrender.  Bacon pointed to examples of what implied surrender usually looks like, including:
  • James Lichoulas Jr., 124 F.E.R.C. ¶ 61,255, P 23 (implied surrender found where “the building over the substructure generating facilities [had] been demolished, the generating equipment [was] covered with collapsed building materials, and the wicket gate operators of the turbines appear[ed] to be inoperable.”), on reh’g, 125 F.E.R.C. ¶ 61,195 (2008)
  • New England Fish Co., 38 F.E.R.C. ¶ 61,106, at 61,285 (1987) (finding surrender where the licensee “abandoned good-faith operation of the project in 1964” and “never filed an application for new license when the term of the original license expired in 1977.”)
  • Pinedale Power & Light Co., 38 F.E.R.C. ¶ 61,036 (1987) (finding surrender where the licensee abandoned the project 15 years prior to the surrender decision and sold the property 12 years prior to it).
Bacon then argued that current energy policy still favors the development of suitable waterways, and that it could continue (or resume) producing low-cost renewable power from the project.

The case remains pending before the Commission.