Showing posts with label national forest. Show all posts
Showing posts with label national forest. Show all posts

FERC requires licensure of Alaska hydropower project

Monday, February 1, 2016

What happens when federal hydropower regulators discover an unlicensed project subject to their jurisdiction?  A recent case involving a dam at a remote Alaskan fish hatchery ended with an order requiring the project owner to pursue licensure.

At issue is the Hidden Falls Lake Project, located within the Tongass National Forest on Kasnyku Bay on the eastern shore of Baranof Island near Sitka, Alaska.  The project is owned by the Alaska Department of Fish and Game, who installed a 250-kilowatt generator and related equipment in 1982 to power its Hidden Falls fish hatchery.  (A nearby larger Kasnyku Lake project contemplated by the federal government in 1969 never came to fruition.)

Most non-federal hydropower projects in the U.S. must be licensed by the Federal Energy Regulatory Commission.  Under section 23(b)(1) of the Federal Power Act, a non-federal hydroelectric project without a still-valid pre-1920 federal permit must be licensed if it:
(a) is located on a navigable water of the United States;
(b) occupies lands or reservations of the United States;
(c) utilizes surplus water or waterpower from a government dam; or
(d) is located on a stream over which Congress has Commerce Clause jurisdiction, is constructed or modified on or after August 26, 1935, and affects the interests of interstate or foreign commerce.
Part of the Hidden Falls Lake project -- the intake, penstock, 250-kW hydroelectric generator, powerhouse, and distribution lines -- are located on U.S. Forest Service lands. The Forest Service’s documentation states that a minor license application for the Hidden Falls Lake Project was filed with the Commission in 1981, but the Commission said it did not have any records of this application or of any subsequent Commission jurisdictional determination for this project.

But FERC did apparently know about the project.  In 1989, seven years after the project's generator was installed, the Commission initiated an investigation into the jurisdictional status of the project, suggesting it was "unlicensed" or "unauthorized."  Yet that unlicensed hydropower project investigation docket then went dormant until 2015.  Last year, the Forest Service informed the Commission that it had identified the project while conducting environmental reviews in support of a renewal of the Alaska agency's special use permit for the hatchery.  Thus the investigation resumed.

The Commission issued its final order in the case on January 28, 2016.  Because the project intake, penstock, hydroelectric generator, powerhouse, and distribution lines occupy public lands of the United States, the Commission concluded that the Alaska agency must obtain a license for construction, maintenance, and continued operation of the Hidden Falls Lake Project.  The Commission ordered the Alaska agency to file within 90 days a schedule for submitting a license application within 36 months.

If a small hydropower project on a remote Alaskan island is subject to FERC licensure, how many other unlicensed hydropower projects might be out there?  How many other unlicensed hydropower projects might there be on Forest Service or other federal lands?  While FERC investigations of unlicensed hydropower projects are relatively rare, with most years seeing only a handful of public active investigations, could there be other existing projects like the Hidden Falls Lake Project?

Northern Pass proposes new transmission plan

Monday, August 24, 2015

The developer of a proposed $1.4 billion electric transmission line connecting Quebec to New Hampshire has released a revised route for the project, following public opposition to earlier plans.  The new vision for the Northern Pass project would bury more of the line underground and reduce the project's overall capacity to haul power.  Will this version of the Northern Pass gain more traction?

First proposed in 2009, the Northern Pass would be a 192-mile high-voltage direct current (HVDC) transmission line.  It would bring up to 1,000 megawatts of power from Canadian power plants into New England, running from the Canadian border to a proposed converter terminal in Franklin, New Hampshire.  From there, a new alternating current (AC) transmission line would deliver the energy to New England’s electric grid at an existing substation in Deerfield, New Hampshire. 

Since it was first proposed, the Northern Pass route has drawn criticism; the project was delayed, and despite revisions to the route public opposition remained.  Throughout the process, many comments have focused on local siting impacts, like the effect of above-ground transmission lines and poles through Franconia Notch State Park, the White Mountain National Forest, and the Appalachian Trail.  Eversource proposed running 8 miles of cable underground to reduce these impacts, but argued that undergrounding more would make the project too expensive.

But the forces motivating the Northern Pass project and other proposed HVDC lines from Canada remain strong: demand in New England and New York for electricity, and in particular for hydropower and other renewable electricity imported from Canada.

On August 18, project lead Eversource Energy announced changes to the route and scope of the project.  While the previous vision included 8 miles of underground cable to avoid visual impacts, the so-called "Forward New Hampshire Plan" now includes 60 miles of underground cable. Eversource described its revised route as striking "a balance between New Hampshire and our region’s need for a reliable new energy source and avoiding potential impacts to the state’s scenic landscapes."  At the same time, the revised proposal reduces the line's capacity from 1,200 megawatts to 1,000 megawatts, ostensibly to hold total costs at the previously estimated $1.4 billion.  The plan now includes $200 million to establish the "Forward NH Fund", a pool of money designed to support clean energy innovations, economic development, community investment, and tourism.

The Northern Pass project now faces public hearings.  Eversource is expected to file an application for site review with the New Hampshire Site Evaluation Committee in mid-October.