DesertLink transmission project wins rate incentives under Section 219

Tuesday, August 23, 2016

Federal energy regulators have granted a petition by the developer of a proposed electric transmission project in Nevada for certain transmission rate incentives available under federal law.  On August 19, the Federal Energy Regulatory Commission ruled on DesertLink, LLC's petition for declaratory order, with respect to DesertLink's new Harry Allen to Eldorado 500 kV transmission project.  The order grants DesertLink's requests for transmission rate incentives under section 219 of the Federal Power Act, and illustrates how those incentives operate.

DesertLink, a member of the LS Power Group, is the developer of a transmission project to be located in Nevada, but connected to a substation in the grid controlled by the California Independent System Operator Corporation.  CAISO designated the project for competitive bidding under its 2013-2014 transmission plan, and in January 2016 selected DesertLink as the approved project sponsor under its Order No. 1000-based process for eligible transmission developers to submit bids to develop and construct certain transmission projects.  The project is designed to have an in-service date of May 2020.

Rate incentives can be available to promote capital investments in certain transmission infrastructure.  The Federal Power Act authorizes the Federal Energy Regulatory Commission to regulate the transmission and wholesale sales of electricity in interstate commerce.  Through the Energy Policy Act of 2005, Congress added a new section 219 to the Federal Power Act, directing the Commission to create rules establishing incentive-based rate treatments.  The Commission's Order No. 679 sets forth the processes by which a public utility may seek transmission rate incentives under section 219, and the Commission has issued a Transmission Incentives Policy Statement offering guidance on how it evaluates applications for transmission rate incentives.

Section 219 and Order No. 679 require an applicant for rate incentives to show that “the facilities for which it seeks incentives either ensure reliability or reduce the cost of delivered power by reducing transmission congestion.”  Order No. 679 established a rebuttable presumption that this standard is met if:
(1) the transmission project results from a fair and open regional planning process that considers and evaluates the project for reliability and/or congestion and is found to be acceptable to the Commission; or (2) a project has received construction approval from an appropriate state commission or state siting authority.
Order No. 679 also requires an applicant to demonstrate that there is a nexus between the incentive being sought and the investment being made.  The Commission clarified in Order No. 679-A that this "nexus test" is met when an applicant demonstrates, on a project-specific basis, that the total package of incentives requested is “tailored to address the demonstrable risks or challenges faced by the applicant.”

In DesertLink's case, on May 11, 2016, the applicant applied for transmission rate incentives, including (1) deferred recovery of all prudently incurred precommercial costs through the creation of a regulatory asset (regulatory asset incentive); (2) full recovery of 100 percent of prudently-incurred costs, including pre-commercial expenses and construction costs, if the Project is abandoned for reasons beyond DesertLink’s control (abandonment incentive); (3) use of a hypothetical capital structure consisting of 50 percent debt and 50 percent equity until the Project achieves commercial operation (hypothetical capital structure incentive); and (4) a 50-basis point adder to DesertLink’s Return on Equity (ROE) for participating in a Regional Transmission Organization (RTO), namely, CAISO (RTO participation incentive).

Last week, the Commission granted DesertLink's petition.  First, the Commission found that DesertLink is entitled to the rebuttable presumption that the Project will ensure reliability or reduce the cost of delivered power by reducing transmission congestion, because the CAISO transmission planning process found annual production cost benefits of $9.4 million in 2019 to $8.4 million in 2024 and beyond, and annual capacity benefits of $19.7 million in 2020 to $8.8 million in 2025 and beyond.

Next, the Commission found that DesertLink had demonstrated that its total package of requested incentives is tailored to address the demonstrable risks or challenges faced by DesertLink.  The Commission found that the regulatory asset treatment of pre-commercial costs appropriately addresses the risks and challenges of the Project, because it provides DesertLink with added upfront regulatory certainty, reduces interest expenses, and assists in the construction of the Project.  On the abandonment incentive, the Commission found that recovery of abandonment costs was an effective means to encourage transmission development by reducing the risk of non-recovery of costs.  Regarding a hypothetical capital structure, the Commission noted that its use "will aid DesertLink in raising capital during the construction phase of the Project, and will assist DesertLink in maintaining low debt costs while its actual debt-to-equity ratio varies."  The Commission also found DesertLink would qualify for the RTO participation incentive, based on its commitment to become a member of CAISO and to transfer operational control of the project to CAISO after placing it in service.

The Commission's determination takes the form of a declaratory order granting authorization for the rate incentives, but it does not directly authorize DesertLink to include the incentives in its filed rates.  As the Commission noted, "While our determination on DesertLink's Petition establishes whether it qualifies for the requested transmission rate incentives, if DesertLink seeks to put these incentives into effect, it must submit a subsequent filing under section 205 of the FPA."  In such a case, the applicant will need to make a variety of showings before including certain incentives in its rate base, including the justness and reasonableness of costs relating to pre-commercial, formation, and plant abandonment.  Nevertheless, securing the declaratory order gives DesertLink greater certainty about its qualification for these key incentives for electric transmission development.

FERC to examine competitive transmission incentives

Wednesday, March 23, 2016

The Federal Energy Regulatory Commission has scheduled a Commissioner-led technical conference for this summer to discuss issues related to competitive transmission development processes.  At issue will be the use of cost containment provisions, the relationship of competitive transmission development to transmission incentives, and other ratemaking issues.

As part of the Energy Policy Act of 2005, Congress added section 219 to the Federal Power Act.  Section 219 directs the Commission to establish, by rule, incentive-based rate treatments to promote capital investment in certain transmission infrastructure.  The Commission's Order No. 679 sets forth processes by which a public utility may seek transmission rate incentives pursuant to section 219.  To qualify, an applicant must show that "the facilities for which it seeks incentives either ensure reliability or reduce the cost of delivered power by reducing transmission congestion" and also demonstrate a nexus between the incentives being sought and the investment being made.  Order No. 679-A clarified that this nexus test is satisfied when an applicant demonstrates that the total package of incentives requested is tailored to address the demonstrable risks or challenges faced by the applicant.

But a case decided earlier this year has led the Commission to reevaluate broader policy considerations relating to the role of cost containment proposals in competitive transmission development.   In a January 8, 2016 order, NextEra Energy Transmission West, LLC, 154 FERC ¶ 61,009, the Commission partially rejected a request by a public utility transmission owner for certain transmission rate incentives pursuant to section 219 and Order No. 679.  That case involved proposed transmission development under the California Independent System Operator Corporation (CAISO)'s competitive transmission developer selection process adopted to comply with Order No. 1000.

Most controversial in the "NEET West" case was a conditional adder to the utility's return on equity that would be triggered if the return on equity fell below the 10 percent that was the foundation for the utility's competitive bids for transmission project development.  On the specific facts and circumstances of that case, the Commission found that the utility had not provided adequate support for the "conditional ROE incentive" and therefore denied it.

But in ruling on the NEET West case, the Commission noted that "this case highlights broader policy considerations related to the potential benefits of cost containment proposals in the context of competitive transmission development." In the NEET West order, the Commission signaled its intent to convene a technical conference in the future to explore further such issues, including how they relate to a 2012 Policy Statement issued by the Commission providing additional guidance regarding its evaluation of applications for transmission rate incentives under section 219 of the Federal Power Act and Order No. 679.

The first specific issue identified in the NEET West order involves the relationship between an expectation stated in the Policy Statement and risks associated with cost containment proposals. The Policy Statement requires an applicant seeking an incentive ROE to demonstrate that the proposed project faces risks and challenges that are not either already accounted for in the applicant’s base ROE or addressed through risk-reducing incentives.  The Commission expressed interest in exploring more broadly "why cost containment-related risks would not be accounted for in a base ROE level below 10 percent and yet would be accounted for in a base ROE of 10 percent" as NEET West argued.

The second specific issue involves "whether and how risks voluntarily assumed through submittal of a cost containment proposal relate to the second expectation set forth in the Policy Statement." The Commission expects an applicant seeking an ROE incentive based on a project’s risks and challenges to demonstrate that it is taking appropriate steps and using appropriate mechanisms to minimize its risks during project development.  But it noted that NEET West "voluntarily submitted cost caps to make its bids to CAISO more attractive, which exposes NEET West’s shareholders to risks they would not have faced absent the cost caps."  The Commission expressed intent to explore "whether and how voluntarily assuming this type of risk is consistent with minimization of risk envisioned by the Policy Statement."

On March 17, the Commission denied a request by ITC Grid Development for a declaratory order on whether cost-capped bids that won a competitive transmission project selection process should automatically be considered just and reasonable.  But that same day, the Commission issued a Notice of Technical Conference in Docket No. AD16-18-000.  In a footnote, the notice states that topics to be discussed include, but are not limited to, those that the Commission described in its NEET West order.

The technical conference to explore these and related issues has now been scheduled for June 27 and 28, 2016, at the Commission ’s headquarters at 888 First Street, NE, Washington, DC 20426.