A 124-mile natural gas transmission pipeline proposed from Pennsylvania to New York has received its final environmental impact statement from federal regulators, finding that while the project would cause some adverse environmental impacts but that mitigation would reduce them to less-than-significant levels.
The proposed Constitution Pipeline is designed connect natural gas supplies in northern Pennsylvania with major northeastern markets. Proposed by Constitution Pipeline Company, LLC, a group whose investors include Williams, Cabot Oil & Gas, Piedmont Natural Gas, and WGL Holdings, the 30-inch underground pipeline would have a design capacity of 650,000 dekatherms of natural gas per day. Constitution has pitched the project as a response to natural gas
market demands in the New York and the New England areas, and interest from natural gas shippers that
require transportation capacity from Susquehanna County, Pennsylvania to the existing Tennessee Gas
Pipeline Company LLC (TGP) and Iroquois systems in Schoharie County, New York.
Developing an interstate natural gas pipeline requires a series of federal, state, and local approvals. Under the federal Natural Gas Act, interstate pipelines must obtain a Certificate of Public Convenience and Necessity from the Federal Energy Regulatory Commission prior to construction. Constitution started the pre-filing process in April 2012, and filed its certificate application under Section 7(c) of the Natural Gas Act with the FERC on June 13, 2013.
Under the National Environmental Policy Act, federal agencies must analyze and
document the environmental effects of proposed federal actions such as issuing a certificate of public convenience and necessity for an interstate pipeline. For the Constitution Pipeline and its associated Wright Interconnect compressor transfer station, FERC staff evaluated the projects' impacts on natural resources including geology, soils, groundwater, surface water, wetlands, vegetation, wildlife, fisheries, special status species, land use, visual resources, socioeconomics, cultural resources, air quality, noise, and safety. Staff considered the projects' cumulative impacts along with other past, present, and reasonably foreseeable actions in the projects’ area. Staff also evaluated over 400 alternatives to the projects, including the "no-action" alternative, system alternatives, major and minor route alternatives, and minor route variations. In a collaborative effort, FERC staff also collected input from cooperating agencies including the U.S. Environmental Protection Agency, the U.S. Army Corps of Engineers, the Federal Highway Administration, and the New York State Department of Agriculture and Markets.
FERC staff issued their Final Environmental Impact Statement, or EIS, for the Constitution Pipeline and Wright Interconnect projects on October 24, 2014. In that document, staff concluded that construction and operation of the Constitution Pipeline and the associated Wright Interconnect would result in some adverse environmental impacts, but these impacts would be reduced to less-than-significant levels with the implementation of mitigation measures proposed by the company and additional measures proposed by FERC. These mitigation measures include implementing plans for upland erosion control, revegetation, and maintenance plan, protecting wetlands and waterbodies, spill plans for oil and hazardous materials, an organic farm protection plan, and a karst mitigation plan. FERC staff also proposed an environmental inspection and mitigation monitoring program to ensure compliance with all mitigation measures that become conditions of the FERC authorizations and other approvals.
For the Constitution Pipeline project, the EIS represents a relatively favorable recommendation by FERC staff to the Commissioners. The ultimate decision whether FERC will issue the project a certificate rests solely with the Commissioners themselves, but regulators typically rely heavily on their technical staff's evaluation of environmental impacts. Likewise, while FERC's final EIS is not necessarily binding on cooperating agencies, they may adopt it if it satisfies their own statutory mandates for environmental reviews.
While the applicants had initially proposed to start construction in 2014, FERC staff acknowledged that "the proposed dates for the start of construction are no longer feasible." Constitution now proposes to start construction in February of 2015 and continue through
the end of 2015, pending receipt of all applicable federal authorizations. The Federal Energy Regulatory Commission may rule on the projects' certificate applications as early as late November this year.
Showing posts with label CPCN. Show all posts
Showing posts with label CPCN. Show all posts
Constitution Pipeline environmental impact statement
Monday, October 27, 2014
FERC approves Maryland LNG project
Tuesday, September 30, 2014
A proposed Maryland natural gas liquefaction facility won a key federal approval yesterday, as the Federal Energy Regulatory Commission authorized Dominion Cove Point LNG, LP to build the Cove Point Liquefaction Project in Calvert County, Maryland, and related facilities
at an existing compressor station and at metering and regulating sites
in Virginia.
Natural gas is an important fuel used globally for electric power generation and heating. While pipelines offer the most efficient way to transport large volumes of natural gas, liquefied natural gas or LNG can more easily be transported by ship to distant markets. As US natural gas production has increased in recent years, so too has interest in building facilities to liquefy gas for export or other use.
Under Section 3 of the Natural Gas Act, the Federal Energy Regulatory Commission or FERC authorizes the siting and construction of onshore and near-shore LNG import or export facilities. Section 7 of the Natural Gas Act authorizes FERC to issue certificates of public convenience and necessity for LNG facilities engaged in interstate natural gas transportation by pipeline.
On April 1, 2013, Dominion applied to the FERC for approval under Section 3 of the Natural Gas Act to site, construct, and operate the Cove Point Liquefaction Project for the liquefaction and export of domestically-produced natural gas at Dominion’s existing LNG import terminal in Calvert County, Maryland. Dominion also requested authority under section 7(c) of the Natural Gas Act to construct and operate facilities at its existing compressor station and metering and regulating sites in Virginia. Collectively, the project will enable Dominion to transport up to 860,000 dekatherms per day of natural gas form existing pipeline interconnects near the west end of the Cove Point Pipeline to the Cove Point terminal for the export of up to 5.75 metric tons of liquefied natural gas per year.
Dominion's requests triggered a case that stretched for over two years of consideration. During this time, the FERC heard from more than 140 speakers at three public meetings related to an assessment of the project's environmental impacts, and received more than 650 comments from the public and federal, state and local agencies on the application. In the end, the FERC determined that Dominion’s proposal, as approved with 79 specific conditions required by the Commission’sauthorization, will minimize potential adverse impacts on landowners and the environment.
According to the FERC, Dominion proposes to complete construction of the liquefaction project so that facilities may start service in June 2017. Notably, the U.S. Department of Energy has already approved Dominion Cove Point’s export of gas to both Free Trade Agreement and non-Free Trade Agreement countries.
The same economic forces motivating the Dominion project support other proposed LNG export projects. Indeed, FERC has approved three other LNG export projects, all in the Gulf of Mexico -- the Sabine Pass Liquefaction Project, the Freeport LNG Project, and the Cameron LNG Project -- and 14 more LNG export proposals remain pending.
Natural gas is an important fuel used globally for electric power generation and heating. While pipelines offer the most efficient way to transport large volumes of natural gas, liquefied natural gas or LNG can more easily be transported by ship to distant markets. As US natural gas production has increased in recent years, so too has interest in building facilities to liquefy gas for export or other use.
Under Section 3 of the Natural Gas Act, the Federal Energy Regulatory Commission or FERC authorizes the siting and construction of onshore and near-shore LNG import or export facilities. Section 7 of the Natural Gas Act authorizes FERC to issue certificates of public convenience and necessity for LNG facilities engaged in interstate natural gas transportation by pipeline.
On April 1, 2013, Dominion applied to the FERC for approval under Section 3 of the Natural Gas Act to site, construct, and operate the Cove Point Liquefaction Project for the liquefaction and export of domestically-produced natural gas at Dominion’s existing LNG import terminal in Calvert County, Maryland. Dominion also requested authority under section 7(c) of the Natural Gas Act to construct and operate facilities at its existing compressor station and metering and regulating sites in Virginia. Collectively, the project will enable Dominion to transport up to 860,000 dekatherms per day of natural gas form existing pipeline interconnects near the west end of the Cove Point Pipeline to the Cove Point terminal for the export of up to 5.75 metric tons of liquefied natural gas per year.
Dominion's requests triggered a case that stretched for over two years of consideration. During this time, the FERC heard from more than 140 speakers at three public meetings related to an assessment of the project's environmental impacts, and received more than 650 comments from the public and federal, state and local agencies on the application. In the end, the FERC determined that Dominion’s proposal, as approved with 79 specific conditions required by the Commission’sauthorization, will minimize potential adverse impacts on landowners and the environment.
According to the FERC, Dominion proposes to complete construction of the liquefaction project so that facilities may start service in June 2017. Notably, the U.S. Department of Energy has already approved Dominion Cove Point’s export of gas to both Free Trade Agreement and non-Free Trade Agreement countries.
The same economic forces motivating the Dominion project support other proposed LNG export projects. Indeed, FERC has approved three other LNG export projects, all in the Gulf of Mexico -- the Sabine Pass Liquefaction Project, the Freeport LNG Project, and the Cameron LNG Project -- and 14 more LNG export proposals remain pending.
Labels:
Calvert,
certificate,
comments,
conditions,
Cove Point,
CPCN,
Dominion,
export,
interstate natural gas,
LNG,
Maryland,
natural gas,
Natural Gas Act,
pipeline,
process,
transport,
Virginia
Subscribe to:
Posts (Atom)
