Two South Carolina utilities have announced their decisions to cease work on two
new
nuclear
units
under construction at the V.C. Summer Nuclear Station in Jenkinsville, South Carolina.
The project to develop Units 2 and 3 at the V.C. Summer plant was led by contractor Westinghouse Electric Co. LLC, but has experienced years of delay and billions of dollars in cost overruns. Westinghouse filed for Chapter 11
bankruptcy protection in March 2017, placing the project's future in question.
On July 31, 2017, South Carolina Electric & Gas Company (SCE&
G), principal subsidiary of
SCANA Corporation (SCANA) and owner of 55% of the plant under construction, announced that it will cease construction at the V.C. Summer site "and will
promptly
file a
petition
with the Public
Service Commission of South Carolina seeking approval of
its abandonment plan." According to a press release, "SCE&G concluded that it would
not be in the best interest of
its
customers
and
other stakeholder
s
to continue construction of the project." Factors cited in SCE&G's press release include "the additional costs to complete the Units, the
uncertainty regarding the availability of production tax credits for the project,
the amount of anticipated
guaranty settlement payments from Toshiba Corporation (Toshiba),
and other matters associated with
continuing construction
, including
the decision of
the
co-owner
of the project
,
the South Carolina Public
Service Authority (Santee Cooper), the state owned electric utility,
to
suspend
construction of
the project."
Project co-owner Santee Cooper also issued a press release on July 31 announcing its decision to suspend construction of the units. Santee Cooper cited "a
comprehensive analysis of detailed schedule and cost data, from both
project contractor Westinghouse Electric Co. and subcontractor Fluor
Corp., first revealed after Westinghouse, filed for bankruptcy in March." According to Santee Cooper, to date it has spent about $4.7 billion in construction and
interest costs, but its analysis shows the project would not be finished until
2024 (four years later than Westinghouse's latest estimate) for a total cost to Santee Cooper's customers of $11.4 billion.
The V.C. Sumner project was one of two new nuclear projects under commercial development in the U.S. The other project, at Plant Vogtle, was also being developed by Westinghouse. Its fate remains uncertain.
No comments:
Post a Comment