A report released by the U.S. Government Accountability Office found that U.S. and Canadian electricity suppliers have taken steps to prepare for potential electromagnetic disruptions to the electric grid such as from solar storms or high-altitude nuclear detonations -- but that more research is needed on both geomagnetic disturbances and high-altitude electromagnetic pulses.
Under some circumstances, a severe solar storm or high-altitude nuclear
blast could damage the U.S. electric grid and potentially cause
extensive outages. Federal energy regulators have used both regulatory and more informal collaborative approaches to address the threat to the electric grid posed by electromagnetic pulses and geomagnetic disturbances. Regulatory approaches to electromagnetic disturbance readiness include mandatory reliability standards adopted by electric reliability organization NERC, which require some electricity suppliers to assess their
vulnerability to extreme solar storms, and developing procedures for responding to grid security emergencies.
In this context, the Government Accountability Office was asked to
review electricity
industry actions to prepare for and
mitigate electromagnetic
risks. Its 95-page report, Critical Infrastructure Protection: Electricity Suppliers Have Taken Actions to Address Electromagnetic Risks, and Additional Research is Ongoing, examines
topics including the degree to which U.S. and Canadian
electricity generation and transmission owners and operators have identified
information about
the effects on the grid caused by geomagnetic disturbances and high-altitude electromagnetic pulses (HEMP), steps some suppliers
have taken to protect against GMD and
HEMP, and opportunities for U.S. suppliers to recover costs for
protecting against GMD and HEMP.
According to the report, there is
"general
agreement
that
more research is needed
on
both
GMD and HEMP." Risks identified include potential
voltage instability leading to collapse
of the bulk power system and
blackouts, as well as possible
damage to key
system components. But more information is needed, according to the report -- especially on HEMP effects, given that previous studies have focused on impacts to military equipment as opposed to the commercial electric grid.
The cost of addressing reliability concerns can be significant. The GAO report describes some suppliers' reports "that costs they have incurred to
protect against
GMD and HEMP have been relatively small so far and they expect
to recover
those costs through customer rates." But the report warns that suppliers
could face future increased costs, as a second regulatory standard phases in through 2022. For example,
the report cites one supplier serving about 4.5 million retail customers as estimating "the cost of hardening a planned
control center against HEMP to be at least $10 million." GAO calculated that fully passing this cost on to customers in a single year would add $2 to the average customer
’s electric bill
for that year.
While regulated U.S. suppliers may be able to recover GMD protection costs through rates, the report notes that recovery is less certain for protection against HEMP because
less is known about HEMP risks. The report also presages challenges for any kind of reliability-driven cost recovery for independent
owners of power plants, who must
recover
reliability improvement
costs through their sales of
electricity
without assurances about market prices.
No comments:
Post a Comment