US first tidal project to come online

Wednesday, September 12, 2012

The nation's first commercial, grid-connected tidal energy project is scheduled to go live this month, as Ocean Renewable Power Company plans to start delivering power to the grid from its Cobscook Bay Tidal Energy Project.

A scene from the Maine coast: Crow Island off Great Cranberry Island, about 100 miles west of the Cobscook Bay Tidal Energy Project.

Earlier this year, the Federal Energy Regulatory Commission issued an pilot project license to Ocean Renewable Power Company Maine, LLC for its Cobscook project near Eastport, Maine.  The initial phase of ORPC's project involves a hydrokinetic turbine connected to a generator capable of producing up to 180 kilowatts of energy; after monitoring this turbine for a year, ORPC plans to expand the project to a capacity of 3 megawatts.

ORPC also won a 20-year power purchase agreement to sell the projects' output to Maine's three large electric utilities at a price escalating from 21.5 cents per kilowatt-hour.  That PPA was the result of a Maine law creating a competitive process for marine renewable energy developers to secure offtake agreements.

In a filing with the FERC earlier this week, ORPC announced that it anticipates delivering power from the Cobscook project to the mainland Bangor Hydro Electric Co. grid starting today.  According to the filing, this initial power delivery is part of the project's commissioning phase, with commencement of commercial operation expected by September 20.

Hydrokinetic projects -- generating electricity from tides, waves, and free-flowing rivers -- is a new sector of the U.S. energy portfolio.  Studies suggest that hydrokinetic resources have great potential, with tidal energy's electric production potential estimated to be 2.38 terawatt-hours per year, equal to an average power of 270 MW.  Wave energy appears to provide the larger resource, with an estimated electricity production potential of about approximately 260 TWh/yr (equal to an average power of 30,000 MW), with river in-stream electricity production potential estimated at approximately 110 TWh/yr.

FERC issues wave energy license

Monday, August 20, 2012

Federal energy regulators have issued a license to a wave energy project off the Oregon coast.  If built as proposed, the project could be the first grid-tied commercial-scale wave energy project in U.S. waters.

A sailboat cruises past the Bear Island Lighthouse near Northeast Harbor, Maine.
Last week the Federal Energy Regulatory Commission issued a license (76-page PDF) to Reedsport OPT Wave Park, LLC for the ocean energy project.  In its license application filed in January 2010, the Ocean Power Technologies, Inc. subsidiary proposed a buoy-based wave energy conversion project to be located about 2.5 nautical miles off the coast of Reedsport, in Douglas County, Oregon.  Water depths in the project area range from about 204 to 225 feet.

According to the FERC order issuing the project's license, the project will generate electricity from using ten PowerBuoy wave energy converters anchored to the seafloor.  Each buoy will have a 150 kilowatt nameplate capacity; physically, each buoy has a maximum diameter of 36 feet, extends 29.5 feet above water, and has a draft of 115 feet.
 
The marine renewable energy project will be built in two phases.  In the first phase, a single PowerBuoy will be installed; this will enable the developer to test the mooring system and buoy operation, as well as to study the electromagnetic fields and acoustic emissions produced by the project.  This single buoy will not be connected to the grid.  After at least one season of monitoring this single buoy, the developer will add up to nine additional PowerBuoys and connect the array to the mainland grid. The ten buoy units will be deployed in an array of three rows about 330 feet apart, with a footprint of about 30 acres.

The developer reportedly expects to install the first buoy by the end of 2012, with the remaining generators to be installed by 2015.  FERC's license for the project has a term of 35 years.