A tidal energy project proposed off the Washington coast will be scrapped due to cost overruns, according to the project developer.
Public Utility District No. 1 of Snohomish County's proposed Admiralty Inlet Pilot Tidal Project was envisioned as a temporary, experimental project to evaluate
the commercial viability of tidal energy development in Puget Sound. The 600-kilowatt
hydrokinetic project would have generated electricity from the force of water moving through turbines mounted in tidal currents. Earlier this year, the project won a pilot license from the Federal Energy Regulatory Commission, making it among the first tidal projects to qualify for the Commission's pilot licensure program.
But the estimated costs of the project were significant relative to its projected energy output. Since it was first proposed in 2006, the Public Utility District estimated that the project would cost $20 million to build. Based on these numbers, the Commission estimated that the levelized annual cost of
operating the project would be about $1,848,294. Dividing this by the project's expected production of energy, the power could cost $7,574.98 per
megawatt-hour of energy generated -- an amount over 250 times higher than the
estimated $30/MWh cost of alternative power.
Nevertheless, the PUD had designed the project's finances to avoid the need for ratepayer financing. Rather, the project relied on
funding from federal grants and in-kind
contributions from project partners, as well as some money from
the sale of excess renewable energy credits from the District's wind power projects. To date, the District has invested about $3.5 million in the effort, over the past 8 years.
With the FERC license in hand, the District moved forward to solicit bids for project engineering and construction. When those bids came in, the District realized the project would likely cost closer to $37 million, or $17 million more than previously expected. According to a September 30 announcement by the Public Utility District, the District tried to seek more funding for the project from the U.S. Department of Energy and other project partners, but did not succeed. As a result, the District has announced that it will not move forward with the project.
While the District is no longer actively pursuing the Admiralty Inlet Pilot Tidal Project, some other developer may try to pick up where the District left off. Indeed, the District's announcement notes that the project "remains worthwhile to pursue on behalf of
the nation to further the potential development of marine renewable
energy." Will another developer seek to advance the Admiralty Inlet Pilot Tidal Project? Will other tidal current and marine hydrokinetic projects be developed given the challenges of ocean energy project economics?
Showing posts with label Snohomish. Show all posts
Showing posts with label Snohomish. Show all posts
Washington tidal energy project cancelled
Thursday, October 2, 2014
Labels:
Admiralty Inlet,
current,
Department of Energy,
district,
DOE,
FERC,
grant,
hydropower,
PUD,
Puget Sound,
REC,
Snohomish,
tidal,
Washington,
wind
Hydrokinetic energy projects in 2014
Wednesday, April 2, 2014
Hydrokinetic energy projects generate electricity from moving water, capturing the power embodied in tides, waves, and currents without the use of dams. Hydrokinetic energy resources are estimated to have a tremendous power potential -- according to one U.S. Department of Energy study, approximately 1,420 terawatt-hours per year, or approximately one-third of the nation's total annual electricity usage. The technologies required are relatively new, do not have decades of operational experience, and remain relatively expensive. Nevertheless, federal records show growth in hydrokinetic project development.
The Federal Energy Regulatory Commission regulates most hydrokinetic energy projects under its hydropower jurisdiction pursuant to the Federal Power Act. Project developers may seek preliminary permits granting the right to study a particular site and priority to apply for a project license.
Relatively few projects have received licenses to date. In 2012, the Commission issued a pilot project license for the Roosevelt Island Tidal Energy project in the East River near New York City. Last month, the Commission issued a pilot project license to the Public Utility District No. 1 of Snohomish County for a 600 kilowatt tidal project in Puget Sound, Washington.
As of last month, six projects have been issued preliminary permits that remain in effect:
The Federal Energy Regulatory Commission regulates most hydrokinetic energy projects under its hydropower jurisdiction pursuant to the Federal Power Act. Project developers may seek preliminary permits granting the right to study a particular site and priority to apply for a project license.
Relatively few projects have received licenses to date. In 2012, the Commission issued a pilot project license for the Roosevelt Island Tidal Energy project in the East River near New York City. Last month, the Commission issued a pilot project license to the Public Utility District No. 1 of Snohomish County for a 600 kilowatt tidal project in Puget Sound, Washington.
As of last month, six projects have been issued preliminary permits that remain in effect:
- Ecosponsible, Inc.'s Niagara Community project, a 1.25 megawatt inland project proposed for the Niagara River in New York
- Ecosponsible, Inc.'s Niagara Community #2 project, a similar 1.25 megawatt inland project proposed for the Niagara River in New York
- Iguigig Village Council's Iguigig RISEC project, a 40 kilowatt inland project proposed for the Kvichak River in Alaska
- The Town of Edgartown, Massachusetts's Muskeget Channel Tidal Energy project, a 4.94 megawatt project proposed for the Muskeget Channel off the island of Martha's Vineyard
- Turnagain Arm Tidal Energy's Turnagain Arm Tidal project, a 240 megawatt tidal project proposed for Cook Inlet, Alaska
- Resolute Marine Energy, Inc.'s Yakutat project, a 750 kilowatt wave project proposed in the Gulf of Alaska
Labels:
Alaska,
current,
Ecosponsible,
FERC,
hydrokinetic,
island,
license,
Martha's Vineyard,
New York,
Niagara,
pilot project,
preliminary permit,
river,
Roosevelt Island,
Snohomish,
tidal,
Washington,
wave
Snohomish tidal project wins FERC pilot license
Friday, March 21, 2014
Federal regulators have issued a pilot license for a proposed tidal energy project in Washington.
Yesterday, the Federal Energy Regulatory Commission issued a 10-year pilot license to Public Utility District No. 1 of Snohomish County for the proposed Admiralty Inlet Pilot Tidal Project. The 600-kilowatt hydrokinetic project, to be located in Puget Sound in the state of Washington, is designed as a temporary, experimental project to evaluate the commercial viability of tidal energy development in Puget Sound.
According to the Commission's Order Issuing Pilot Project License (85-page PDF), the proposed project features two tidal turbines to be manufactured by OpenHydro, each measuring 6 meters in diameter, secured to the seabed by the turbines' 414-ton weight. Peak tidal currents at the site exceed 3 meters per second. The Public Utility District plans to connect the project to the mainland grid via subsea cables connecting to District-leased land south of the Coupeville Ferry Terminal.
In granting the pilot license, the Commission considered a range of possible resource impacts from the project. The site lies near key shipping lanes to the ports of Seattle, Tacoma, Olympia, and Everett, and is near a key trans-oceanic fiber optic cable connecting North America to Japan. To address concerns over impacts to these resources, the Commission imposed conditions and monitoring requirements on the project.
The Commission's pilot licensure program differs somewhat from its general licensing of hydropower projects. As described in a whitepaper on the pilot project licensing process prepared by Commission staff, pilot projects should be (1) small; (2) short term; (3) located in non-sensitive areas based on the Commission’s review of the record; (4) removable and able to be shut down on short notice; (5) removed, with the site restored, before the end of the license term (unless a new license is granted); and (6) initiated by a draft application in a form sufficient to support environmental analysis. Projects meeting these criteria enjoy a streamlined regulatory review process.
With the pilot license in hand, the Public Utility District may prepare for project development. But if the project goes forward, the District may have to justify its costs. As noted in the Commission’s order, the project has relatively high capital, operation, and maintenance costs with respect to the amount of power produced. According to the Commission’s order, the levelized annual cost of operating the project will be about $1,848,294, or $7,574.98 per megawatt-hour of energy generated -- significantly higher than the estimated $30/MWh cost of alternative power. Based on an estimated average annual generation of 244,000 kilowatt-hours as licensed, Commission staff projects that in the first year of operation, the project power will cost $1,840,974 more than the cost of alternative power.
Admittedly, the Snohomish project is designed as an experiment -- a pilot project to test technology and project feasibility. The Snohomish project is among the first hydrokinetic projects in the country to receive a FERC license. The first pilot project issued for a tidal project, the Roosevelt Island Tidal Energy Project, similarly faces projected above-market energy costs. Like the Roosevelt Island project, the Snohomish project will be relatively small. But given its financial picture, will the Snohomish project go forward?
![]() |
| Tidal waters off the Maine coast. |
According to the Commission's Order Issuing Pilot Project License (85-page PDF), the proposed project features two tidal turbines to be manufactured by OpenHydro, each measuring 6 meters in diameter, secured to the seabed by the turbines' 414-ton weight. Peak tidal currents at the site exceed 3 meters per second. The Public Utility District plans to connect the project to the mainland grid via subsea cables connecting to District-leased land south of the Coupeville Ferry Terminal.
In granting the pilot license, the Commission considered a range of possible resource impacts from the project. The site lies near key shipping lanes to the ports of Seattle, Tacoma, Olympia, and Everett, and is near a key trans-oceanic fiber optic cable connecting North America to Japan. To address concerns over impacts to these resources, the Commission imposed conditions and monitoring requirements on the project.
The Commission's pilot licensure program differs somewhat from its general licensing of hydropower projects. As described in a whitepaper on the pilot project licensing process prepared by Commission staff, pilot projects should be (1) small; (2) short term; (3) located in non-sensitive areas based on the Commission’s review of the record; (4) removable and able to be shut down on short notice; (5) removed, with the site restored, before the end of the license term (unless a new license is granted); and (6) initiated by a draft application in a form sufficient to support environmental analysis. Projects meeting these criteria enjoy a streamlined regulatory review process.
With the pilot license in hand, the Public Utility District may prepare for project development. But if the project goes forward, the District may have to justify its costs. As noted in the Commission’s order, the project has relatively high capital, operation, and maintenance costs with respect to the amount of power produced. According to the Commission’s order, the levelized annual cost of operating the project will be about $1,848,294, or $7,574.98 per megawatt-hour of energy generated -- significantly higher than the estimated $30/MWh cost of alternative power. Based on an estimated average annual generation of 244,000 kilowatt-hours as licensed, Commission staff projects that in the first year of operation, the project power will cost $1,840,974 more than the cost of alternative power.
Admittedly, the Snohomish project is designed as an experiment -- a pilot project to test technology and project feasibility. The Snohomish project is among the first hydrokinetic projects in the country to receive a FERC license. The first pilot project issued for a tidal project, the Roosevelt Island Tidal Energy Project, similarly faces projected above-market energy costs. Like the Roosevelt Island project, the Snohomish project will be relatively small. But given its financial picture, will the Snohomish project go forward?