Northern Pass Transmission public utility status

Thursday, October 27, 2016

New Hampshire utility regulators have issued an order conditionally authorizing Northern Pass Transmission LLC to operate as a public utility, with respect to its proposed 192-mile, high-voltage electric transmission line from Canada into New Hampshire.  The New Hampshire Public Utilities Commission's Order No. 25,953 approves a settlement agreement between the transmission line developer and Commission staff.  Among its conditions are requirements that NPT obtain all necessary permits, contribute $20 million over 10 years to support energy efficiency and clean energy initiatives, and hold New Hampshire electric ratepayers harmless from costs associated with the possible regional allocation of costs for a portion of the Northern Pass transmission line.

Proposed by two companies affiliated under the Eversource family -- Northern Pass Transmission LLC and Public Service Company of New Hampshire d/b/a Eversource Energy -- the Northern Pass line would include new direct current transmission lines and an AC-DC converter station.  A variety of federal and state approvals are required for the line's development, including certification of site and facility by the state Site Evaluation Commission, plus several approvals from the Public Utilities Commission.

NPT secured one of those approvals this month, in the form of Public Utilities Commission Order No. 25,953, which conditionally authorizes NPT to operate as a public utilities in municipalities along its route.  In the Order, the Commission found "that NPT has the necessary technical, managerial, and financial expertise to operate as a public utility."

The Commission next found that the terms and conditions of a settlement agreement between Commission staff and NPT "ensure that granting NPT authority to commence business as a public utility is for the public good."
  • First, the Commission noted public benefit, in the form of transparency, from the fact that the settlement recites a list of applicable statutes and rules.
  • Second, the settlement called for a $20 million public interest payment, to be paid in installments of $2 million per year over the first 10 years of the operation of the Northern Pass Project; the Commission noted that this payment "will benefit customers by allowing the Commission to direct the use of this payment to energy efficiency programs and clean energy projects under its supervision."
  • Third, the Commission noted that its grant of public utility status is conditioned on NPT procuring all necessary approvals for the Northern Pass Project, including obtaining a certificate of site and facility from the SEC.
  • Finally, the Commission noted a provision in the settlement that "NPT must hold New Hampshire electric ratepayers harmless from costs associated with the possible regional allocation of costs for a portion of the Northern Pass transmission line."  The Commission expressed a belief "that the rate treatment provision applicable to the DC portion of the line could constitute a significant benefit to ratepayers in the event the ISO-NE designates this portion as eligible for regional cost recovery.
On this basis, the Commission approved the settlement agreement in its entirety, adopted its conditions, and found that commencement of business as public utility subject to those terms and conditions will be for the public good.

Meanwhile, NPT continues to pursue other approvals, such as PUC approval for crossings of public waters, and the SEC certificate of site and facility itself.

NHPUC considers PSNH divestiture auction format

Thursday, September 15, 2016

As the New Hampshire Public Utilities Commission prepares for an auction of the state's largest utility’s generating assets, its auction advisor J.P. Morgan has recommended a broad public auction of the assets, using a two phase structure.

At issue are the generation facilities owned by Public Service Company of New Hampshire d/b/a Eversource Energy (Eversource).  Following a legislative finding that divestiture is in the public interest at the present time, on July 1, 2016, the Commission issued Order No. 25,920 approving the 2015 Public Service Company of New Hampshire Restructuring and Rate Stabilization Agreement and the Partial Litigation Settlement Agreement. Those settlement agreements called for the Commission to open an expedited proceeding to oversee the process of auctioning the Eversource generation facilities.

On September 7, 2016, the Commission opened a proceeding to implement the divestiture process for the generation facilities of Eversource as approved in Order 25,920. In its Order of Notice opening the auction process docket, the Commission noted a primary objective of obtaining the highest possible sale value of the generation facilities in order to minimize the level of stranded costs ultimately paid by Eversource customers. It also noted a secondary objective, to the extent not inconsistent with the primary objective, to accommodate the participation of municipalities that host generation assets and to fairly allocate among individual assets the sale price of any assets that are sold as a group.

A report recently filed in the docket by Commission staff presents recommendations from its advisor J.P. Morgan on the auction design and process.  According to the report, these recommendations were designed to maximize the overall value of the transaction and the likelihood of the successful sale of each asset.

In Phase I, Eversource, the Commission, and its advisor would develop of a list of potential bidders who would be invited to respond to a Request for Qualifications (RFQ). Parties satisfying the requirements of the RFQ would be asked to execute a confidentiality agreement, after which they could review a Confidential Information Memorandum. This document would provide certain limited information about the assets, to let bidders develop a preliminary non-binding indication of interest. The report suggests this phase could take six weeks from launch to the submission of preliminary, non-binding proposals – potentially spanning from November 2016 into January 2017.

In Phase II, bidder indications of interest would be used to identify potential bidders likely to transact on terms most favorable to the seller. These “second round” bidders would have access to full due diligence. The report suggests allowing about 8 weeks for Phase II parties to conduct due diligence, mark up a draft purchase and sale agreement, and submit a final, binding proposal. The report suggests Phase II might run from January 2017 into March 2017.

Following the submission of final bids, the report suggests that the Commission select one or two parties per asset or group of assets for final negotiations, depending on the level of interest.

Written comments on the auction design and process are due by September 30, 2016. The Commission has said that the proceeding will culminate in a decision on auction results, and if necessary, a financing order authorizing securitization of stranded costs and stranded cost rates.

NH net metering bills passed

Thursday, March 17, 2016

The New Hampshire legislature is acting to expand that state's net metering programs.  Now the question is how much: a 50% expansion, or a doubling?

New Hampshire law requires electric distribution utilities to offer eligible customer-generators a standard tariff for net energy metering. Solar panels are the most commonly net metered type of generation, but other technologies are also used.  Net metering under these tariffs is available "on a first-come, first-served basis within each electric utility service area" until each utility hits its specific cap on net metered capacity.  Under existing law, each utility's cap is effectively its share of a statewide program cap of 50 megawatts.

On January 20, 2016, utility Eversource announced it had reached its cap, and that it would place new projects going forward on a wait list.  But New Hampshire is home to significant interest in expanding net metering.  In the same announcement, Eversource described its work with the state legislature "to enact an expansion to the net metering program."  As the utility said, "Such an expansion would alleviate much of the uncertainty being faced by customers and developers, and would provide time for stakeholders to investigate all of the various costs and benefits of distributed generation and to provide for a sustainable evolution of the net metering program."

Meanwhile, Eversource also indicated a request that state regulators "develop a more permanent solution to the challenge of fairly compensating developers of new distributed generation in a manner that does not shift costs to other customers."

In February, the New Hampshire Senate voted to increase the net metering cap from 50 megawatts to 75 megawatts.  That bill, S.B.333, also directed the New Hampshire Public Utilities Commission to develop a net metering tariff for all generation above the 75 megawatt cap.

This month the New Hampshire House passed H.B.1116, a bill that would double the cap, to 100 megawatts.

Under New Hampshire legislative process, these two bills must be reconciled before a proposal can be sent to Governor Maggie Hassan.  But she has expressed strong support for reconciling the bills and expanding net metering:
Lifting the cap on net metering is essential to the continued success of New Hampshire’s solar industry, and I applaud the House for its bipartisan vote to pass this critical measure. The Senate has already supported this legislation, and I urge them to concur with the version passed by the House and send this bill to my desk as quickly as possible so that we can lift the cap on net metering.
The New Hampshire House and Senate now have the opportunity to reconcile the bills and present them to Governor Hassan for her signature.  Assuming this happens, New Hampshire will significantly expand its net metering program in the near term.