Demolition of the Great Works dam on Maine's Penobscot River began this morning. The dam removal marks the first major physical change to the Penobscot riverscape following the 2004 Lower Penobscot Basin Comprehensive Settlement Accord. This landmark agreement led the Penobscot River Restoration Trust to acquire two dams on the river for $24 million - the Great Works and Veazie dams - and ultimately to the dams' removal.
The Great Works dam was originally built in the late 1800s to provide water and waterpower to a series of lumber and paper mills. Over time, hydroelectric facilities were added to the dam. By its end, the facility included a powerhouse
containing 11 turbine-generator units totaling about 8 MW of installed
capacity.
Although the dam included several fish passage facilities, environmentalists and fishery agencies considered the river's overall fish passage structures and accessible habitat inadequate. After years of advocacy and negotiations, in 2004 seven conservation groups, the Penobscot Indian Nation, state and federal agencies and then-dam owner PPL agreed to a comprehensive settlement that would remove the Great Works and Veazie dams but allow six other dams
that will remain on the Penobscot and its tributaries to produce more
electricity.
After the Great Works dam removal is complete, the Veazie dam 7 miles downstream will be next to be removed, the Howland Dam on
the upstream tributary Piscataquis River will be decommissioned and bypassed, and a fish lift will be installed at the Milford Dam. Overall, the project is estimated to cost $62 million.
Showing posts with label settlement agreement. Show all posts
Showing posts with label settlement agreement. Show all posts
Penobscot River dam removal starts
Monday, June 11, 2012
February 28, 2011 - dam removal costs and values
Monday, February 28, 2011
Dam removal can bring environmental benefits, but comes with costs. These costs can include not only the expense of physically breaching the dam and removing its remains, but also costs associated with sampling and remediating contaminated sediments trapped behind the dam. Here's a quick look at two case studies, providing updates on stories I've noted before.
Last November, I looked at what's trapped behind dams on South Carolina's Twelve Mile Creek near Clemson. Polychlorinated biphenyls (PCBs) and other chemical contaminants from electronics manufacturing operations have become trapped in sediments behind several dams slated for removal. Removal of the dams is expected to allow cleaner sediments to flow down into Lake Hartwell where they are hoped to be able to cap the PCB-contaminated lake bottom. Work on a sediment storage area is now ongoing along Twelve Mile Creek, funded through the $9 million settlement in the enforcement lawsuit against the manufacturer.
Just over a year ago, I noted that a settlement agreement would lead to the removal of four hydro-electric dams on the Klamath River in California and Oregon. There, utility PacifiCorp has agreed to undertake the dam removal, which is projected to commence in 2020. Overall, the Klamath Basin Restoration Agreement and Klamath Hydroelectric Settlement Agreement contemplate a dam removal cost of $450 million, with another $1 billion in environmental restoration activities. How will dam removal be paid for? At least part of the funds (albeit a relatively small share) will likely come from PacifiCorp's ratepayers. A California administrative law judge has recommended that the California Public Utilities Commission approve a nine-year 2 percent rate increase to raise $13.8 million for dam removal. Where the rest of the money will come from, as well as whether U.S. Secretary of the Interior Ken Salazar decides to support dam removal, remains to be seen.
Last November, I looked at what's trapped behind dams on South Carolina's Twelve Mile Creek near Clemson. Polychlorinated biphenyls (PCBs) and other chemical contaminants from electronics manufacturing operations have become trapped in sediments behind several dams slated for removal. Removal of the dams is expected to allow cleaner sediments to flow down into Lake Hartwell where they are hoped to be able to cap the PCB-contaminated lake bottom. Work on a sediment storage area is now ongoing along Twelve Mile Creek, funded through the $9 million settlement in the enforcement lawsuit against the manufacturer.
Just over a year ago, I noted that a settlement agreement would lead to the removal of four hydro-electric dams on the Klamath River in California and Oregon. There, utility PacifiCorp has agreed to undertake the dam removal, which is projected to commence in 2020. Overall, the Klamath Basin Restoration Agreement and Klamath Hydroelectric Settlement Agreement contemplate a dam removal cost of $450 million, with another $1 billion in environmental restoration activities. How will dam removal be paid for? At least part of the funds (albeit a relatively small share) will likely come from PacifiCorp's ratepayers. A California administrative law judge has recommended that the California Public Utilities Commission approve a nine-year 2 percent rate increase to raise $13.8 million for dam removal. Where the rest of the money will come from, as well as whether U.S. Secretary of the Interior Ken Salazar decides to support dam removal, remains to be seen.
December 21, 2010 - Penobscot River dam removal one step closer
Tuesday, December 21, 2010
The plan to remove several hydroelectric dams on the Penobscot River reached a milestone yesterday: transfer of ownership of three dams from PPL to the Penobscot River Restoration Trust. The Trust plans to remove the Veazie and Great Works dams, while building fish passage at the Howland dam. By removing the two dams and generation assets, about 16 MW of renewable capacity will be removed from the grid, although permitted increases in power production upstream are expected to recover this capacity.
The sweeping Penobscot River dam removal project arose from a 2004 settlement agreement called the Lower Penobscot Basin Comprehensive Settlement Accord. In that settlement, seven conservation groups, hydroelectric company PPL Corp., the Penobscot Indian Nation and state and federal agencies, agreed to the removal of both the two dams as well as the removal of flashboards and the installation of a fish bypass at the Howland Dam.
![]() |
| The lower Penobscot River seen from Fort Knox in Prospect, about 25 miles downstream from the dams to be removed. |