FERC policy on hydropower license term

Thursday, October 26, 2017

U.S. hydropower regulators have issued a new policy setting a default term of 40 years for original and new hydropower licenses, while identifying three circumstances that could warrant longer or shorter terms.  The Federal Energy Regulatory Commission's revised policy statement on establishing license terms could reduce cost and uncertainty for hydroelectric projects under its jurisdiction.

Federal law gives the Federal Energy Regulatory Commission jurisdiction over licensing most hydroelectric projects located at non-federal dams.  Section 6 of the Federal Power Act authorizes the Commission to issue hydropower licenses for a term not to exceed 50 years, but leaves the Commission some discretion to issue licenses for shorter terms.  

Prior to the October 19, 2017 policy statement, the Commission’s policy for projects located at non-federal dams was to offer a 30-year term where there is little or no authorized redevelopment, new construction, or environmental mitigation and enhancement; a 40-year term for a license involving a moderate amount of these activities; and a 50-year term where there is an extensive amount of such activity.  The Commission has found that measures including the construction of pumped storage facilities, fish passage facilities, fish hatcheries, substantial recreation facilities, dams, and powerhouses warranted longer license terms.

But after licensees and other stakeholders contested license terms in several recent cases, on November 17, 2016, the Commission issued a notice of inquiry seeking comments on whether, and if so how, it should revise its license term policy in effect at that time. As characterized by the Commission, most hydropower industry commenters supported the certainty offered by longer default terms, while most environmental groups, individuals, and resource agencies opposed them on various grounds.

On October 19, 2017, the Commission issued its Policy Statement on Establishing License Terms for Hydroelectric Projects. The new policy establishes a 40-year default license term for original and new licenses under the Commission’s jurisdiction with exceptions for coordination, deference to generally-supported comprehensive settlement agreements, and consideration of previously-authorized voluntary actions.  According to the policy statement, these exceptions will apply:
  • When necessary to coordinate license terms for projects located in the same river basin;
  • When a license term is explicitly agreed upon in a generally supported comprehensive settlement agreement, provided that there is no conflict with coordination of license terms for projects located within the same river basin; and
  • When significant measures are required under the license to be issued, or significant measures were voluntarily implemented during the prior license term, provided it does not conflict with coordination of license terms for projects located within the same river basin.
According to a presentation by Commission staff, the new policy "will provide greater certainty to licensees, resource agencies, and other stakeholders," will reduce administrative costs and provide licensees longer license terms to recoup costs, and could encourage licensees to voluntarily make improvements or agree with stakeholders to a license settlement agreement.

According to the Commission, it will apply this new policy to licenses issued following the date of its publication in the Federal Register with no retroactive application.  While the Commission said it would not entertain applications to amend existing licenses to extend their license terms simply on the basis of this new license term policy, it noted that license applicants with pending license applications may file a comprehensive settlement agreement, or an addendum to an existing agreement, that includes an explicitly agreed upon license term, or may make a filing demonstrating why the Commission should award them a longer license term.

RC Byrd hydro project licensed at Army Corps locks and dam

Wednesday, August 30, 2017

Federal hydropower regulators have issued an original license to an Ohio city to construct, operate, and maintain a 50-megawatt hydroelectric project at an existing U.S. Army Corps of Engineers lock and dam site.  If developed as licensed, the City of Wadsworth, Ohio's Robert C. Byrd Hydroelectric Project will join other projects focused on adding hydroelectric generation to existing dams.

The Army Corps owns 21 locks and dams on the Ohio River, which it operates for commercial and recreational navigation.  These facilities include the RC Byrd Locks and Dam, originally built in the 1930s and renovated within the past 25 years.

On March 28, 2011, the City of Wadsworth, Ohio, applied to the Federal Energy Regulatory Commission for a license to construct, operate, and maintain the Robert C. Byrd Hydroelectric Project No. 12796.  As proposed by the city, the project would include new intake and tailrace structures along with a powerhouse holding two turbine generator units with a total installed capacity of 50 megwatts, but not the existing Army Corps dam.

On August 30, 2017, the Federal Energy Regulatory Commission issued its Order Issuing Original License for the RC Byrd Project.  The license, which authorizes the installation of 50 MW of new, renewable energy generation capacity, requires a number of measures to protect environmental resources at the project, including measures proposed by the licensee as well as additional terms and conditions developed by Commission staff and other agencies. 

According to the licensing order, the project will generate approximately 266,000 megawatt-hours per year, with a levelized annual cost of constructing and operating the project of about $40,586,280, or $152.58/MWh.  While the Commission found this to be more expensive than the cost of alternative power in the first year of licensure, the Commission also noted "that hydroelectric projects offer unique operational benefits to the electric utility system."  These ancillary service benefits "include the ability to help maintain the stability of a power system, such as by quickly adjusting power output to respond to rapid changes in system load; and to respond rapidly to a major utility system or regional blackout by providing a source of power to help restart the fossil-fuel generating stations and put them back on line."

Consistent with the Commission's general policy regarding license term for projects located on a federal dam, the Commission issued the RC Byrd Project license for a term of 50 years, the maximum allowable under the Federal Power Act.

If developed as licensed, the RC Byrd Project would be part of a trend toward adding hydroelectric generating facilities to existing dams owned by the Army Corps or other dam owners.  Congress and the Commission, as well as state agencies, have expressed support for adding hydropower to existing dams and lock structures.

FERC and microhydro licensing

Wednesday, May 18, 2016

Federal energy regulators have ruled that a micro-hydroelectric project proposed in New York cannot be constructed or operated without a license.

The proposed Henson Micro Hydroelectric Project would be located on the West Branch of Onondaga Creek, near Onondaga, New York.  It would include an existing 14-foot-high concrete dam, plus new construction including a penstock, a powerhouse, and a 10 kilowatt generating unit.  The dam was rebuilt in 2002, and had previously been used to power a grist mill.  The project developer, an individual, proposed to use the project power to provide electricity to his home and barn.
 
In his declaration of intention, the developer described himself and his approach to project development and compliance:
I would like to point out that I am not a corporation, or a rich man just a simple middle class Joe. I am an hourly employee at AT&T. Although blessed beyond what I actually deserve, I do not have a bunch of money that I could spend. In fact I am using funds recently obtained from a loss of use settlement from the NYS Workers Compensation Board to fund this. I am trying to do the right thing for the environment and save some money on my power bill. I am hoping that we can work this out to everyone’s satisfaction based upon the material and information that I currently have available. Of course, if additional information is required by you folks I will do everything to comply.
Identifying what approvals are necessary is a core step in developing any project.  Under section 23(b)(1) of the Federal Power Act, a non-federal hydroelectric project must be licensed by the Federal Energy Regulatory Commission (unless it has a still-valid pre-1920 federal permit) if it:
(a) is located on a navigable water of the United States;
(b) occupies lands or reservations of the United States;
(c) utilizes surplus water or waterpower from a government dam; or
(d) is located on a stream over which Congress has Commerce clause jurisdiction, is constructed or modified on or after August 26, 1935, and affects the interests of interstate or foreign commerce.
To reduce uncertainty over whether a project will require licensing, a developer may file a Declaration of Intention with the FERC describing the project.  Following public notice and an opportunity for protests, comments, and motions to intervene, FERC will rule on the jurisdictional questions raised by the declaration.

In the Henson project's case, the developer filed a Declaration of Intention on December 18, 2015.  That declaration was supplemented; after the second supplement, FERC issued its public notice of the declaration.  No protests, comments, or motions to intervene were filed.

On May 10, FERC issued its ruling on the declaration, finding that licensing is required.  FERC easily found that the project would not occupy any public lands or reservations of the United States or use surplus water or waterpower from a Federal government dam.  It found "insufficient evidence" to determine whether the West Branch of the Onondaga Creek is navigable.

However, FERC found that the West Branch of Onondaga Creek is a headwater or tributary of the Oswego River, a navigable water of the United States.  As a result, FERC concluded the project would be located on a "Commerce Clause stream."  FERC noted the project would be constructed after 1935.

FERC also concluded that the project would affect interstate commerce through its connection to the interstate grid, relying on precedent that "small hydroelectric projects that are connected to the interstate grid affect interstate commerce by displacing power from the grid, and the cumulative effect of the national class of these small projects is significant."  Thus even though the Hanson project's developer proposed using project power for the onsite home and barn, the fact that those buildings were grid-tied drove FERC to conclude that licensing was required. 

On this reasoning, FERC concluded that construction, operation, and maintenance would require a license.  As an alternative, FERC suggested the developer consider applying for an exemption from licensing as a small hydroelectric power project.


By contrast, another recent FERC decision concluded that a micro-hydro system proposed in Massachusetts did not require licensing, because (among other reasons) neither the project nor the structures it would serve would be grid-tied.  Thus whether or not the project and the facilities it serves are grid-tied or off-grid can be an important factor in whether a FERC hydropower license is required.

FERC tests 2-year hydropower licensing process

Wednesday, August 6, 2014

Licensing some new hydropower projects in the United States -- traditionally a lengthy process -- may soon become easier, as federal regulators have approved an experimental two-year process that may soon be used to license some projects.

Water spills over a small, non-powered dam in Maine.

The Federal Energy Regulatory Commission regulates most hydropower development in the United States.  Under Part I of the Federal Power Act, the Commission considers applications for hydropower project licenses.  While the traditional licensure process has resulted in the issuance of thousands of licenses, winning a license for a project can take many years -- and some licensure proceedings have stretched toward a decade.

In response to concerns that lengthy licensing procedures stifle hydropower development, last year Congress enacted the Hydropower Regulatory Efficiency Act of 2013.  That law directed the Commission to investigate the feasibility of a two-year licensing process for certain projects, develop criteria for identifying projects that may be appropriate for the process, and develop and implement pilot projects to test the process.

In January 2014, the Commission solicited pilot projects to test a two-year process.  Two kinds of projects were eligible: hydropower development at existing non-powered dams and closed-loop pumped storage projects.  In the notice soliciting pilot projects, the Commission articulated additional criteria for eligibility including:
  • The project must cause little to no change to existing surface and groundwater flows and uses;

  • The project must not adversely affect federally listed threatened and endangered species;

  • If the project is proposed to be located at or use a federal dam, the request to use the two-year process must include a letter from the dam owner saying the plan is feasible;

  • If the project would use any public park, recreation area, or wildlife refuge, the request to use the two-year process must include a letter from the managing entity giving its approval to use the site; and

  • For a closed-loop pumped storage project, the project must not be continuously connected to a naturally flowing water feature. 
Ultimately, the Commission selected a project proposed by Free Flow Power Project 92, LLC: a 5-megawatt project at the Kentucky River Authority's existing Lock & Dam No. 11 on the Kentucky River in Estill and Madison counties, Kentucky.  Lock and Dam 11 were originally built from 1904-1906 and support a twenty mile long pool of water 201 miles above the mouth of the Ohio River, but have not previously supported a FERC-licensed hydropower project.

The Free Flow Power applicant's request to use the 2-year licensing process was filed on May 5, 2014, so the two years runs through May 5, 2016.  The Commission staff has issued a process plan and schedule with interim milestones through February 2016.  Compared to a traditional licensure process, the proposed schedule is accelerated -- but will this pilot case remain on schedule?  Will the accelerated process satisfy the various stakeholders, including the developer, regulator, neighbors, and public?

spring-fed small hydro in Idaho?

Friday, April 27, 2012

Small-scale hydroelectric projects are receiving renewed interest as society looks for cost-effective ways to produce electricity using local, renewable resources.  Depending on available sites and on what alterntative resources might be available, microhydro or small-scale hydroelectric projects can fit the bill.  Even if you own a first-class site for a microhydro project, before you can build or operate your project, you need to understand what federal and state regulations may apply.  Some small hydro projects are treated much like full-scale dam-based hydropower projects, while others (like small projects using existing conduits, pipes or canals) can get an easier regulatory path to approval.

A small hydro project proposed near Grace, Idaho illustrates some of these regulatory considerations, and the importance of understanding how regulators apply the rules.  Grace is a town of about 1,000 people located in Idaho's Gem Valley.  The Bear River runs through the valley on its course flowing out of Bear Lake, around the Bear River Range by Soda Springs, and then south through Grace into Utah's Cache Valley.  In the early twentieth century, recognizing the area's water resources and topographic variation, a series of dams, diversion pipes and powerhouses were built along the Bear River to produce hydroelectricity.  One side effect was that a stretch of river known as Black Canyon was largely dewatered, as an aqueduct carried the water around the canyon to a downstream powerhouse.  Ultimately, Utah Power and Light (and then PacifiCorp) came to operate these assets, and chose to remove one of the dams, an aqueduct and one powerhouse in 2006 and 2007, and to provide some increased flows through the Black Canyon section.

There may be ways to generate hydroelectricity in Grace without diverting water away from the Bear River. Last month, a local farmer with interests in canals and hydro development proposed a new hydro project near Grace.  The Gilbert Hydropower Project proposed to capture the flows of several natural springs and pipe this water about 700 feet to a turbine/generator unit.  Currently, the water is partially used for pasture irrigation with the unused portion flowing into the Bear River; the developer proposes to install a 24‐inch diameter above-ground pipeline to send the water to a Pelton turbine attached to a 75 kW generator.

In its application to the Federal Energy Regulatory Commission (docketed by FERC as Project No. 14367-000), the project developer requested an exemption from the licensing requirements of the Federal Power Act under the so-called "5 megawatt exemption" rule.  That rule allows the Commission to exempt small hydroelectric projects with an installed capacity of 5 megawatts or less that: (1) are located at the site of any dam in existence on or before July 22, 2005, and that use the water power potential of such dam for the generation of electricity; or (2) use a “natural water feature” to generate electricity, without the need for any dam or impoundment.

FERC dismissed the Gilbert project's request for an exemption, noting, "Because [the] project would utilize the flows of a natural spring that travel through 700 feet of pipe to reach the proposed turbine/generator unit, it would neither be at the site of an existing dam nor use the flows from a natural water feature", and thus was ineligible for an exemption.  However, FERC did invite the Gilbert developers to convert their exemption application to a license application, which the developers did earlier this month.  The developers now have until June 18, 2012, to submit the additional information needed for a complete license application.

What's in the future for Grace, Idaho?  What role could using nontraditional water resources such as springs play there or elsewhere in our energy future?

NYC tidal project gets pilot license

Tuesday, January 24, 2012

Federal regulators have issued a pilot project license to a tidal power proposal to be developed in the East River off New York City.  Yesterday the Federal Energy Regulatory Commission awarded a license to the Roosevelt Island Tidal Energy Project (62-page PDF).

As described in the license, the Roosevelt Island project will start relatively small, and is licensed for additional phases of growth.  The first phase entails deployment of three 35-kW Kinetic Hydropower Systems developed by Verdant Power, LLC.  Each of these units has a 5-meter diameter turbine connected to  generator.  Over time, additional turbine units could be deployed, up to a total of 30 turbines, for a total nameplate capacity of 1,050 kilowatts.

Verdant chose to seek a pilot project license for the Roosevelt Island tidal development.  FERC views its hydrokinetic pilot project licensing process as a variant of its Integrated Licensing Process.  Compared to other paths to FERC hydropower licenses, the pilot project process is designed to allow developers to test new hydrokinetic and hydropower technologies while minimizing both their costs and the risk of adverse environmental impacts.

Commission staff have described the ideal pilot project as (1) small, (2) short term, (3) located in environmentally non-sensitive areas based on the Commission’s review of the record, (4) removable and able to be shut down on short notice, (5) removed, with the site restored, before the end of the license term (unless a new license is granted), and (6) initiated by a draft application in a form sufficient to support environmental analysis.  Based on the Roosevelt Island project's similarity to this conceptual ideal, FERC staff recommended that Verdant pursue a pilot project license.

Verdant's pilot project license includes a variety of conditions and mitigation requirements.  Among these are a requirement that Verdant commence construction of Phase 1 within two years, and to complete construction of Phase 3 within six years of the issuance date of the license.  If Verdant meets these deadlines, the Roosevelt Island could be producing electricity within the next few years.

Other innovative ocean energy projects are pursuing FERC's pilot project licensure path, such as the Cobscook Bay Tidal Energy Project proposed by Ocean Renewable Power Company Maine, LLC.  Verdant's license is the first hydrokinetic pilot project license that FERC has issued; others may follow in its footsteps.

Alaska proposes large new dam

Monday, January 9, 2012

The Alaska Energy Authority has filed key documents with federal regulators giving formal notice of its intent to build the proposed 600 megawatt Susitna-Watana Hydroelectric Project.  If this project is approved and built, it will be the largest hydroelectric project developed in the U.S. since 1966.

Plans to develop a large-scale hydropower project on the Susitna river have been considered for decades.  In 2010, the Alaska Legislature established a goal of providing half of the state’s electric power from renewable sources by 2025.  The Alaska Energy Authority, a public corporation of the state whose mission is to use Alaska's natural resources to produce electricity and lower costs, concluded that Alaska could not meet the 50% renewable goal without building a major new hydroelectric project.

On December 29, 2011, the Alaska Energy Authority filed a notification of intent to file an application for a hydroelectric license and a pre-application document with the Federal Energy Regulatory Commission.  FERC docketed the project as No. 14241.  (You can read these documents in FERC's eLibrary here.)

In those documents, the Alaska Energy Authority described the project as located about 180 miles north of Anchorage.  The dam itself would be large: 700 to 800 feet in height, and with a crest length of over 2,700 feet.  The dam would impound a 39-mile-long reservoir, flooding 20,000 acres and capable of storing about 2,400,000 acre-feet.  The Authority plans to install three 200 MW turbine-generator sets for a total installed capacity of 600 MW, but is considering up to 800 MW of capacity.

The Authority expects the FERC hydropower licensing process to take up to 6 years.  The size and impacts of the project make it attractive to some yet controversial to others.  Public comments are already being filed in the FERC docket.

Municipal hydrokinetic energy

Thursday, December 29, 2011

Interest is increasing in municipal hydrokinetic energy projects, as cities and towns consider whether they should generate renewable electricity from their water resources.  Hydrokinetics entails generating electricity from moving water such as tides, waves, and free-flowing rivers.  Towns, states, and national governments may not only have an interest in generating power for their citizens, but may also have advantages in project development such as lower financing costs.

For example, the town of Wiscasset, Maine is considering whether to pursue a project togenerate electricity from tidal power in the Sheepscot River. The town thinks that tidal currents and flowing water in the Sheepscot could be used to generate electricity using hydrokinetic technology.  In 2008, the town applied to the Federal Energy Regulatory Commission for a preliminary permit to study the feasibility of the project. Wiscasset proposed to deploy a series of hydrokinetic turbine generating units in the tidal Sheepscot, along with associated transmission facilities. Currently, Wiscasset appears to be considering using the RivGen units under design by ORPC.

In May 2009, the FERC granted Wiscasset its preliminary permit. Preliminary permits confer the right to investigate the feasibility of a hydropower project, typically for a three-year term. Preliminary permits do not authorize actual construction; to actually build and operate a hydrokinetic or hydroelectric project generally requires a FERC license or exemption. The holder of a preliminary permit does have first priority to file for a full license as long as the preliminary permit remains in effect, and FERC expects permittees to make progress toward ultimate licensure. (For example, in September 2011 a company affiliated with ORPC used its preliminary permit priority to file a pilot license application for the Cobscook Bay Tidal Energy Project.)

Next spring, the town faces a key deadline if it chooses to seek a hydrokinetic pilot project license for the project. Wiscasset’s preliminary permit is set to expire on April 30, 2012. Filings in the project’s FERC docket suggest that the town may seek to extend that deadline. For example, in a May 2011 filing, the town said, “we anticipate the Wiscasset Project will apply for a successive Preliminary Permit in May 2012”.

Generally, preliminary permits expire after three years, after which the original permittee has no special rights to the site. In certain circumstances, federal regulators can grant successive preliminary permits. For example, FERC has given several municipal hydroelectric projects successive preliminary permits when the towns need more time. Even this requires a showing of diligent efforts to investigate the project’s feasibility and partial progress toward readiness for a license application.

In Wiscasset’s case, other deadlines within the preliminary permit process have already been extended. For example, the 2009 preliminary permit required the town to submit a Notice of Intent and draft license application in May 2011. Instead of filing these pre-application documents, the town chose to ask FERC for an extension to allow more site studies and stakeholder consultation. FERC allowed the town more time, but only until the preliminary permit expires on April 30, 2012. FERC may give the town similar leniency if it applies for a successive preliminary permit this spring. On the other hand, FERC promotes competition and discourages “site-banking”; if someone else showed interest in developing the Wiscasset site, FERC might be less inclined to issue the town a successive preliminary permit.

Wiscasset has until the end of April 2012 to either file a license or seek its successive preliminary permit.  If Wiscasset moves forward, the Sheepscot hydrokinetic project could be an example of how towns can benefit from their renewable energy resources.

June 28, 2011 - pending applications for hydrokinetic licenses

Tuesday, June 28, 2011

To wrap up our look at how hydrokinetic power projects are licensed, today I'll consider the currently pending applications for hydrokinetic project licenses.

Hydrokinetic power production entails the production of electricity from the energy of moving water: waves, tides, currents, or river flows.  Commercial projects, and even experimental pilot projects, generally need licenses from the Federal Energy Regulatory Commission.

Because hydrokinetic technologies are relatively new, FERC has issued only two licenses for hydrokinetic projects to date.  Two more license applications are pending, split between wave and tidal energy applications.

The pending hydrokinetic license application for wave energy is for the Reedsport OPT Wave Park in Oregon.  Developer Ocean Power Technologies (OPT) initially submitted its license application in January 2010.  If built, this would be the first commercial wave park on the west coast of the U.S.  The proposal is for an array of up to ten buoys, each of which could produce 150 kW.

The other pending hydrokinetic license application involves a tidal project in Maine.  Developer TideWorks has proposed a 5 kilowatt project in the Sasanoa River, near Bath.  This small project is proposed to provide power to a single-family dwelling on 15-acre Bareneck Island.  Because the project is proposed to have less than 5 MW of capacity, it may qualify for an exemption from licensing -- but must apply to FERC to obtain that exemption.

June 21, 2011 - more on hydrokinetic energy

Tuesday, June 21, 2011

Yesterday, I started a look at the potential of generating electricity from moving water: hydrokinetic energy.
The Doughty Dam in North Berwick, Maine.  The hydropower at this site was responsible for the settling of North Berwick.
Let's say you have a new technology to generate electricity from moving water, and you've found a site where you'd like to try it out.  While you have a limited opportunity to test turbines without getting a license from the Federal Energy Regulatory Commission, most hydrokinetic projects will need to get FERC approvals such as a preliminary permit, license, or exemption from licensing.

A preliminary permit is the traditional first step toward getting a FERC license.  Once you get a preliminary permit, you have first priority to file an application for a full license at that site within three years.  While the permit doesn’t authorize you to build or run the project, it secures your exclusive right to acquire a license for your site during the permit’s term.

The next step is securing a license.  FERC encourages projects, even small or experimental ones, to secure licenses.  In fact, after Verdant Power tested its turbines near New York City for several years, FERC has recommended licensing Verdant Power’s 1 MW Roosevelt Island Tidal Energy (RITE) Project as a pilot project.

Compared to traditional licensing, pilot project status qualifies an applicant for an expedited review process.  Pilot projects must be small; FERC applies a case-by-case determination of whether a project qualifies for a pilot license, so there is no bright line for how big is too big.  Guidance suggests 5 MW is a reasonable size cap, with some projects expected to be “substantially smaller”.

Pilot project licenses are short term – generally 5 years.  Pilot projects are also intended not to be permanent on their own; unless the developer gets a new license before the pilot license expires, the developer must remove the project and restore the site when the pilot license expires.  On the other hand, a pilot project license is one step closer to ultimate licensure, as compared to unlicensed testing.

Hydrokinetic technology holds great promise, and developers are lining up to capitalize on it.  As of June 2011, FERC has issued 70 preliminary permits for hydrokinetic projects, totaling 9,306 MW.  147 more preliminary permit applications are pending – interestingly, 145 of which are on inland waterways.  79 hydrokinetic projects with 8,002 MW capacity have entered the pre-filing process for licensure, with 3 more projects in the post-filing phase.

June 20, 2011 - hydrokinetic power

Monday, June 20, 2011

Flowing water contains large amounts of usable energy.  Beyond traditional dam-based hydroelectric generation, water’s power can be captured using hydrokinetic technology.  A hydrokinetic project generates electricity from moving water: the flow of tides, waves, ocean currents, or unimpounded rivers.  Most hydrokinetic projects will need regulatory approval from the Federal Energy Regulatory Commission, a process that is still evolving but is getting easier over time.

The Oyster River Dam in Durham, NH.


While humans have long recognized the power of moving water, cost-effective technologies for converting this power into electricity are still in their infancy.  The U.S.’s first federally-licensed hydrokinetic project was commissioned in 2009.  This project on the Mississippi River in Hastings, Minnesota features a 100 kW turbine mounted on a barge tethered in the output channel of an existing hydropower plant: the Army Corps of Engineers’ 4.4 MW Lock & Dam 2.  Under typical operating conditions, the Hastings project produces 35 kilowatts of power.

Technology continues to evolve rapidly, and each new design has to be tested.  Under limited circumstances, developers can test turbines without obtaining a FERC license.  In 2005, dealing with Verdant Power’s testing of underwater turbines in the East River in New York City, FERC ruled that a license is not required for a hydrokinetic project if the technology is experimental; the proposed facilities will be used for a short period for studies needed to seek a license; and the power generated from the test project will not be transmitted into, or displace power from, the electric grid.

This opportunity to test turbines without a license is limited.  Most hydrokinetic projects will need to get FERC approvals such as a preliminary permit, license, or exemption from licensing.  Tomorrow, I'll look at some of those paths toward developing and operating a renewable hydrokinetic energy project.

October 11, 2010 - permitting small and low-impact hydropower projects

Monday, October 11, 2010

As states and the federal government implement policies to promote both renewable power production and greater energy independence, small and low-impact hydropower projects provide a relatively accessible way to participate and benefit from these favorable policies. Today we'll take a walk through three different paths to getting approval from the Federal Energy Regulatory Commission (FERC) for a small hydro project.

First, a quick review of FERC's general licensing procedures. FERC has three licensing processes for hydro projects, all with similar names: the Traditional Licensing Process (TLP), the Alternative Licensing Process (ALP), and the Integrated Licensing Process (ILP).

The TLP is the longest-standing process, with origins dating back to 1935 and Part I of the Federal Power Act. In a TLP, the licensee engages in a three-stage pre-filing consultation process. Once a final application is filed, FERC issues public notice of the application, and solicits comments and intervention by other stakeholders. After further process including an environmental assessment or environmental impact statement, FERC is ready to issue (or deny) the requested license.

While applicants have traditionally used the TLP (hence its name), effective July 23, 2005, the Integrated Licensing Process (ILP) is the default process for filing an application for an original, new, or subsequent license. In fact, Commission approval is now needed to use either the Traditional or the Alternative Licensing Process for larger projects.

The ALP allowed for somewhat more flexibility in the process. For example, in an ALP, an applicant can modify the pre-filing consultation process depending on the circumstances. The ALP allows applicants to streamline the pre-filing consultation process and environmental review processes under the National Environmental Policy Act and other laws. This is achieved in part through a collaborative workgroup to study and resolve issues. Finally, the ALP allows the applicant to prepare a preliminary draft environmental assessment, or allows an environmental impact statement to be drafted by a FERC-selected contractor at the applicant's expense. This allows scoping of environmental issues to occur prior to the application being filed with the Commission. However, the ALP has proved cumbersome in some instances, with a lengthy total process time.

The ILP combines some of the features of both the traditional and alternative processes, including a more formal study development process than under the TLP. This five-year process was adopted by FERC in 2003.

So what about small and low-impact hydropower projects? The Traditional Licensing Process is still used to prepare applications for small projects that qualify for either of two exemptions from FERC's licensing provisions under the Federal Power Act: the "conduit" exemption and the 5-MW exemption.

The conduit exemption operates to simplify the process for a hydropower project on an existing conduit (for example an irrigation canal). Conduit exemptions are authorized for generating capacities 15 megawatts or less for non-municipal and 40 megawatts or less for a municipal project. The conduit has to have been constructed primarily for purposes other than power production and be located entirely on non-federal lands.

Another exemption applies to small hydropower projects, which are 5 megawatts or less, that will be built at an existing dam, or projects that utilize a natural water feature for head or an existing project that has a capacity of 5 megawatts or less and proposes to increase capacity.

August 12, 2010 - FERC hydro relicensing

Thursday, August 12, 2010

FERC staff have recently released a draft Environmental Impact Statement for the existing McCloud-Pit Hydroelectric Project (P-2106-059).  Currently up for relicensing, the 368 MW project is located on the McCloud and Pit Rivers in Shasta County, California.  Licensee Pacific Gas and Electric Company (PG&E) proposed a number of license modifications to enhance environmental protection and recreational opportunities.  Staff countered by recommending those conditions, plus additional protective measures.  The deadline to comment on the draft EIS is September 28, 2010.