Canada's highest court has ruled that Quebec's provincial utility Hydro-Quebec cannot be required to renegotiate a long-term contract to buy power from a Labrador hydroelectric plant at below-market rates, even though the deal has yielded about 14 times more profit for Hydro-Quebec than for the Labrador generator.
At issue is the Churchill Falls hydroelectric plant on the upper Churchill River in Labrador, and a 1969 agreement between Hydro-Quebec and Churchill Falls (Labrador) Corporation Limited -- a company jointly owned by Newfoundland and Labrador Hydro and Hydro-Quebec. The Churchill Falls plant can generate 5,428 megawatts of power, and is one of the world's largest hydroelectric power stations.
According
to former Premier of Newfoundland and Labrador Brian Tobin,
during pre-construction negotiations, Hydro-Quebec told Churchill Falls that it would not allow the Labrador generator to "wheel" project
power through the Hydro-Quebec grid, nor to build its own power line through Quebec to
reach U.S. markets. As a result, under the terms of the 1969 agreement, Hydro-Quebec agreed to buy most of the project's power at the fixed price of $2.50 per megawatt-hour, to guarantee construction cost overruns, and to build transmission lines connecting the generators to markets, enabling the Labrador generator to sell power and to use debt financing to construct the plant. The original contract was set to expire in 2016, but included a renewal
clause allowing Hydro-Quebec to extend the contract for an additional 25
years at a fixed price of $2 per megawatt-hour through 2041.
After the contract was signed, changes in the electricity market -- including oil price shocks in the 1970s, a decline in public confidence in nuclear power after a 1979 accident, and the U.S. Federal Energy Regulatory Commission's 1996 decision to require open access to transmission systems -- meant the contract's purchase price is now well below market prices. Because Hydro-Quebec sells electricity from the plant to third parties
at market prices, Hydro-Quebec reaps substantial profits from the deal. For example, Hydro-Quebec reports that the average retail price for residential customers in St. John's, Newfoundland in 2018 is $120.30 per megawatt-hour. Canada's National Energy Board says the 2017 average wholesale prices for electricity imports were over $24 per megawatt-hour, with exports priced even higher at $38.58 per megawatt-hour -- over 19 times higher than the price Hydro-Quebec now pays Churchill Falls during the extended contract term. According to CBC, the contract has yielded about $28 billion in profits to Quebec, but just $2 billion for Newfoundland and Labrador.
Citing legal theories including a general duty of good faith, Nalcor Energy subsidiary Churchill Falls asked Canadian courts to order that the contract be renegotiated and the benefits be reallocated. After lower courts sided with Hydro-Quebec, the generator appealed to the Supreme Court of Canada.
On November 2, the Supreme Court of Canada rendered its judgment in the matter of Churchill Falls (Labrador) v. Hydro-Quebec. The high court found, by a 7 to 1 decision, for Hydro-Quebec, noting that the parties "bound themselves knowing full well what they were doing" and that Hydro-Quebec could insist on adhering to the contract despite the "unforeseen" increase in the power's market value.
The one dissenting judge characterized the contract as "relational" in nature, and thus said that both parties are subject to a duty of cooperation which Hydro-Quebec breached by failing to renegotiate and to more fully share the benefits of higher-than-expected market prices. He said that because "a profit imbalance of this nature and magnitude is beyond what the parties intended when they concluded the agreement", the parties had an implied obligation to cooperate in establishing a mechanism for the allocation of "extraordinary profits."
No comments:
Post a Comment